Hiccups at Loy Yang A4 (Part 1)
A quick look at 3 successive trips at Loy Yang A4 in returning back from a recent forced outage.
A quick look at 3 successive trips at Loy Yang A4 in returning back from a recent forced outage.
Yesterday (Tue 26th Sept 2023) we saw Kogan Creek drop offline for a few hours - and were asked if this was related to industrial action. Here, with...
It does not happen often, so when receiving 4 different 'coal unit off' alerts within 24 hours, we thought we would take a look ...
CS Energy's Kogan Creek restarted on the morning of Tuesday 20th December 2022.
Prompted by a few media questions (on a day when all 4 units were offline together for about 3 hours), have taken a quick look at the status...
Alerted via an ABC news article, we take a quick look at Callide C3.
A short article, noting trip of Gladstone units 3 and 4 this afternoon.
Adding into the tight supply-demand dynamic, the coal-fired unit Tarong unit 2 tripped this afternoon.
A pretty rare event in the NEM, when two units trip simultaneously ... so a short article on WattClarity as a result.
The publication by AGL Energy of the short note about the transformer incident (and injured worker) at Liddell unit 3 yesterday prompted me to have a quick look,...
Earlier this afternoon we were alerted to a price spike in NSW and QLD that was seemingly caused by a unit trip at one of the larger generators...
Alerted to a price spike at 09:45 this morning in the QLD region, we discovered some reduction in load (spot-exposed Demand Response probably) and also a large collective...
Third case study today - and last one looking back at 2013. This one is a bit more complex than the first two.
Like was the case on 4th July 2013, the cause of this large Aggregate Raw Off-Target result (across all Semi-Scheduled Generators) was a single unit trip.
Does not take long to see why this particular dispatch interval was one of the few dispatch intervals (before 2019!) flagged in our top-down analysis of aggregate Raw...
Following on from Tuesday's main article (summarising results across 105,120 dispatch intervals through 2019 for 'all Coal' and 'all Wind' groupings), this is the first of 4 x...
A quick look at Saturday 11th April (Easter Saturday) where there were major reductions in output at 4 units across Victoria - 3 coal units in the Latrobe...
Guest author, Allan O'Neil does a masterful job with limited time in reviewing some of the goings-on in the NEM (particularly VIC and SA) on Thursday 30th January...
A brief overview of a stressful afternoon/evening in the NEM, where a confluence of events (heatwave-driven high demand, low wind, coal unit trip, etc...) drive LOR2 low reserve...
A quick look after the unit trip (including reported explosion) at Mortlake Unit 2