Case Study (part 1) of Aggregate Scheduled Target on Friday 8th September 2023
The first part of a Case Study looking at a large 5-minute ramp in ‘Aggregate Scheduled Target’ in the middle of the day (an unusual time) on Friday 8th September 2023
The first part of a Case Study looking at a large 5-minute ramp in ‘Aggregate Scheduled Target’ in the middle of the day (an unusual time) on Friday 8th September 2023
A brief article as a first Case Study looking at Mon 3rd and Tue 4th July 2023, in conjunction with the compilation of GenInsights Quarterly Updates for 2023 Q3.
A brief article as a first Case Study looking at Friday 18th August 2023, in conjunction with the compilation of GenInsights Quarterly Updates for 2023 Q3.
With ez2view v9.8.5.1 released yesterday (Tue 30th Sept 2023) with enhancements to ‘Generator Outages’ we take the opportunity of some questions about Kogan Creek Power Station to have a look at the usefulness, and possible additional tweaks to make, to this software widget.
Yesterday (Wed 18th Oct 2023) Origin Energy held its Annual General Meeting, with discussion wide-ranging. Here’s two things that jumped out to me about the Eraring Power Station, which is currently slated to close in 2025.
A quick note to mark the the release of GenInsights Quarterly Update for Q2 2023 last week.
With Q2 drawing to a close, we’re gearing up to produce GenInsights Quarterly Update for this quarter. Timely to look back at Q1 at what was reported about curtailment of wind and solar in that earlier Quarterly Update.
A quick note on Wednesday 31st May 2023 to mark the release of GenInsights Quarterly Update for Q1 2023.
With completion of GenInsights Quarterly Update for Q1 2023 approaching, and following some conversations recently (and probably this week at EUAA Conference) here are two charts looking backwards just at fully dispatchable plant that highlight one of the ways in which ‘the level of risk in the NEM is escalating’.
In today’s article (a third snippet from GenInsights Quarterly Update for Q4 2022) we take a look at levels of large ‘Aggregate Raw Off-Target’ (i.e. large collective deviations away from Target), which continue to grow for the Semi-Scheduled category and remind us of that question …
This second excerpt from GenInsights 2022 Q4 Update highlights some of what’s seen in terms of the performance of coal units.
This first excerpt from GenInsights Quarterly Update for Q4 2022 looks specifically at the trended level of adoption of self-forecasting for Semi-Scheduled Solar Farms in the NEM. This article on Monday 26th February 2023 precedes some changes AEMO might make on Tuesday 27th February 2023.
Drawing from GenInsights Quarterly Update for Q4 2022, and the next version of our ez2view software, we take a look at the *current* expectations for closure of Liddell Power Station (within weeks) and Eraring Power Station (in 2025). A segue into this week’s update to the ESOO, perhaps?
Following an Executive Briefing last week to one client, this week we released the PDF Report for GenInsights Quarterly Update for Q4 2022. Here’s some information to explain what it is.
In GenInsights Quarterly Update for Q3 2022 we included an Appendix exploring what we could observe ‘One Year on from Five Minute Settlement’. In this article we share a small slice of what we learnt…
One of the metrics we introduced into GenInsights Quarterly Update for 2022 Q3 was a long-range review of IRPM (Instantaneous Reserve Plant Margin). In this article we share a little of what we found.
On Monday 31st October 2022 we released GenInsights Quarterly Updates for Q3 2022 – second in the expanding series, following customer requests for updates of GenInsights21
On Monday 1st August 2022 we provided a presentation to the CEC’s Market & Grid Directorate