Fat lady singing for three down (with LD02 on the way out) and one to go at AGL’s Liddell Power Station
A short article to mark the closure of Liddell unit 2 on Wednesday evening, 26th April 2023.
A short article to mark the closure of Liddell unit 2 on Wednesday evening, 26th April 2023.
Alerted by RenewEconomy on social media that Beryl Solar Farm was offline due to bushfires, I used ez2view to take a quick look.
Another short article today presenting an overview of Aggregate Raw Off-Target (AggROT) for Semi-Scheduled units on 16th February 2021 (the largest incidence of collective over-performance at that time).
Another short article today (from GenInsights Quarterly Update for Q3 2022) presenting an overview of Aggregate Raw Off-Target (AggROT) for Semi-Scheduled units on 23rd August 2022.
Another short article today (also from GenInsights Quarterly Update for Q1 2023) presenting an overview of Aggregate Raw Off-Target (AggROT) for Semi-Scheduled units on Friday 20th January 2023.
A short article today (whilst in the midst of finalising GenInsights Quarterly Update for Q1 2023) presenting an overview of Aggregate Raw Off-Target (AggROT) for Semi-Scheduled units on Friday 3rd February 2023.
In an event (that seems) similar to 17th March 2023, a glitch in SCADA leads to the suspension of the market in the Victorian region on Saturday afternoon/evening 22nd April 2023.
Latest data from AEMO (from Fri 14th April) suggests Liddell unit 4 might close a couple days later than when we'd looked in February.
Around eight days till the scheduled closure of Liddell's next-to-close unit (and prompted by an article in the AFR), we take a quick look at how they've been bidding.
The long weekend provided an opportunity to review 10 years of electricity bills at home to look at net usage patterns and net solar injections from our home rooftop solar system. What have we...
It's Easter Sunday (9th April 2023) and it looks like NSW minimum demand has fallen further from the prior record set 6 months ago.
On 6th April 2023 the AEMO published this preliminary report into the brief market suspension that occurred in NSW on 17th March 2023.
AFR and the Australian (and elsewhere?) there are reports of the co-owner of Callide C (with CS Energy) being placed in voluntary administration.
Given the significance of the event (Reserve Trader almost triggered on Thursday 16th March - 34 days till the closure of Liddell Unit 4) we're investing some time in exploring more detail of the...
A quick record of the start of volatility on Sunday evening 19th March 2023.
Looks like a new all-time record for Operational Demand in the QLD region early this evening, Friday 17th March 2023.
Looks like we've (sort of) dodged the Reserve Trader bullet on Thursday evening 16th March 2023 ... but still poses plenty of questions.
Second post for this afternoon/evening following AEMO announcement to commence RERT Negotiations for this evening in NSW.
Some late hot weather (in Autumn 2023) is providing for some activity in the market
From 08:00 (NEM time) this morning, the old 'X5 constraint' (i.e. formerly formally known as 'N^^N_NIL_3') has been split into two (i.e. addressing separately risk of tripping of either/both Bendigo to Kerang 220kV line...