Recovery continues, at Victoria Big Battery
Some activity alerts prompt this short look at how the Victoria Big Battery is recovering from the industrial fire that took it out of action for a number of weeks.
Some activity alerts prompt this short look at how the Victoria Big Battery is recovering from the industrial fire that took it out of action for a number of weeks.
This morning (Fri 8th Oct) the AEMO has released its Incident Report into what happened on 25th May 2021, starting with problems at Callide C4.
Following from some analytical work performed in testing for Five Minute Settlement, here's a view of latency of rebids (all DUIDs, all commodities) in recent months that prompts a number of questions...
A quick look at three price spikes seen late afternoon in QLD on Monday 4th October 2021.
Looks like AEMO will be announcing a new 'lowest point' for Operational Demand in NSW later, given what has happened on Monday 4th October 2021 (Labour Day holiday).
In addition to being a low point for Scheduled Demand and Operational Demand in the QLD region, it was also the case on a NEM-wide basis.
A short note about a new low point for minimum demand that appears to have been set in the QLD region on Sunday 3rd October 2021
It was too tempting to take some time today to look back on the first fully 5-minute bids from Friday 1st October (the start of Five Minute Settlement) to see how much has changed.
It's quite early Friday morning, 1st October 2021 ... and Five Minute Settlement has commenced. Here's a *very* early initial look.
An updated look at return-to-service expectation for the damaged Callide C4 unit.
A quick additional look at activity Tue 28th Sept 2021 for Victoria Big Battery - as seen in ez2view with the benefit of 'Next Day Public' data.
Two separate alerts received today about the Victoria Big Battery sent me looking for more information...
A short back-dated article, to link in AEMO's final report on this incident.
Today (Mon 27th Sept) we were alerted to this Virtual Information Session on Wednesday 29th September that some of our readers will be interested in (Enabling FCAS at Musselroe Wind Farm)
Just last Friday the AEMO notified stakeholders more broadly about their new Market Notice Framework about ‘Minimum System Load’ and/or ‘Distributed Photovoltaics (DPV) Contingency’ ... prior to Sunday's new lowest point for minimum demand...
Sunny skies and mild weather in South Australia on Sunday 26th September sees a new (lower) point for 'Minimum Demand set in the South Australian region.
Following from the ESB's Final Advice, and inspired by the one year anniversary of publications the MT PASA DUID Availability data sets by AEMO (thanks to the ERM-sponsored rule change) we take a quick...
Only ~11 weeks after the end of Q2 2021 we're still exploring details of the extreme price outcomes. Here's some of the ways in which solar PV played a significant role in the price...
[POSTED AT ~13:00] On Sat 11th Sept 2021, the 'Grid Demand' in the NSW region has dropped to levels not seen for many, many years ... especially when considering it is in the middle...
From 10:00 today (Friday 10th September 2021), ElectraNet’s new synchronous condensers (which have been under testing) will be deliver a boost to Semi-Scheduled units in South Australia.