It’s Tuesday morning 7th July 2026 and here’s a snapshot of ‘Bids & Offers’ in ez2view at the 07:45 dispatch interval (NEM time), to highlight that both units at the much-delayed Hunter GT station (a.k.a. Kurri Kurri) gained another test run in recent days:
We see:
- A test run on unit 1 on Friday evening 3rd July 2026; and
- A test run on unit 2 yesterday (Monday evening 6th July 2026)
Yesterday, when the ez2view alerts were triggering to alert me that HUNTER2 had started, I did see that Giles Parkinson had written ‘Snowy warns of “odour and plume” as it commissions diesel generators at delayed and over-budget peaking plant’ yesterday about these tests. That article noted:
‘It says that testing for the commissioning process, due start on Friday, will take place at night, over the course of about four weeks.’
… by which I read ‘due to start on the coming Friday’ (evening 10th July 2026) whereas we see above that there was testing last Friday and last night (so I am a bit confused).
That sent me hunting for the original source from Snowy Hydro – which might be the media release ‘Kurri Kurri Power Station Update’ , which was also published yesterday and notes…
‘Testing is expected to commence on or after Friday, 10 July 2026. It will take place at night, over the course of about four weeks, although the number of nights may change depending on commissioning outcomes.
During diesel testing last year, the intensity of the plume and odour was greater than we anticipated. While there will still be some odour and plume, we do not expect this over an extended period.’
So I am I correct in inferring, from the above, that the ‘test run’ (re the rebid reasons) completed last Friday and last night was on gas and not diesel (hence the apparent discrepancy).