Yesterday we noted ‘TransGrid directed to (temporarily) disconnect 3 batteries for System Strength’.
There are a number of questions that we (and others) are asking – but for now I’d just like to highlight three of them, as follows:
Q1) Why did the batteries take so long to come back online after the event?
In the two market notices referenced in yesterday’s article, it seemed that the event itself lasted only 90 minutes:
1) MN144415 (published at 23:30:20 on Sunday 5th July 2026) noted the required action for TransGrid that:
‘Disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery from the network at 2327 hrs 05/07/2026’
2) MN144418 (published at 00:59:21 on Monday 6th July 2026) noted that:
‘Direction is cancelled from: 0100 hrs 06/07/2026’
… so, from this reading, one might infer that the event was ‘only’ ~90 minutes in duration.
Yet in yesterday morning’s article we noted that the batteries had not yet returned to service. Indeed, in this updated view of the ‘Bids & Offers’ widget in ez2view as at 09:20 (NEM time) on Tuesday 7th July 2026, we see that the batteries did not make it back online (via their bids) until after 16:00 (NEM time) on Monday 6th July 2026:
Whilst we can speculate on a wide range of possible reasons why there was this seemingly large gap (15 hours!) between the direction ending and the batteries returning to service, we’re particularly interested to hear from people who can actually explain more (factually!).
PS (at 11:04) This question answered
Note that the subsequent article ‘An outage on one Darlington Pt 132/330kV transformer the reason … but still more questions’ answers this one.
Q2) Why were they directed off, in the first place?
It’s not just us who are asking this question … both Hieu (here) and then Roger (here) flagged the seeming irony – in that:
- these 3 batteries were touted as helping with System Strength in the weak part of the NSW grid around Darlington Point substation,
- but found themselves all directed offline … for System Strength reasons.
I’ve done a brief amount of digging this morning and thought it might be relevant here to share the following external resources
1) There’s information from ARENA here about the ‘Darlington Point Energy Storage System’.
This page notes, under the heading of ‘Need’ …
‘The project will test the ability of LSBS with advanced inverters to provide a measurable improvement in system strength. If this capability can be successfully demonstrated, LSBS could be used to reduce or eliminate the need for syncons in weak grids. The project is well-positioned to achieve this, as the co-located Darlington Point Solar Farm (DPSF) installed two syncons to remediate system strength and satisfy its grid connection requirements. The syncons will provide a direct comparison between the system strength contributions of the syncons and the project.’
The mention of the (syncons at) nearby DARLSF1 prompts me to take a quick look at the ‘Bids & Offers’ widget in ez2view focused on DARLSF1:
… but it does not look like there’s anything to see here that would explain.
2) There’s also the Edify Energy page(s) about the ‘Riverina and Darlington Point Energy Storage Systems’.
From that page is a link to this ‘Flagship Report: System Strength Remediation’ from 2nd December 2025, but I’ve only skimmed it at very high level. Under the Executive Summary (p5/46) is this extract:
‘The Project has tested the ability of large-scale battery storage with advanced grid forming inverters to provide a measurable improvement in system strength. The Project has demonstrated that grid forming batteries can be relied upon to provide certain system strength services which are required to enable the connection of additional renewable energy generators to the network and to eventually replace the services being provided by conventional synchronous generators (such as coal and gas-powered turbines).
The Project was successful in being the first project in the National Electricity Market (NEM) to navigate the connection process from the beginning using grid forming controls (as opposed to switching to a grid-forming connection after having previously been approved as a grid following connection). The Project has since been successfully tested and commissioned and has been operating commercially since September 2023. ’
However note that, in this brief skim, no answer jumps out at me as to why the 3 x batteries might have been directed off.
3) There’s also this TransGrid sub-site on their ‘System Strength Project’.
This page notes:
‘This project represents the first stage of synchronous condenser deployments in Transgrid’s network, as part of Transgrid’s broader portfolio of solutions to maintain system strength in NSW. The total portfolio of solutions includes ten synchronous condensers, 5 GW of grid-forming BESS and the operation of existing and new synchronous generators to fill gaps in system strength.’
Again – note that whilst we can speculate on a wide range of possible reasons why the direction was made, we’re particularly interested to hear from people who can actually explain more (factually!).
Q3) Has this happened before?
I’ve still not had time to check, but remain curious …
If any of our more learned readers have answers to either (or two, or three) of the above, then ‘we’re all ears’!