It might be the case that this type of action becomes more commonplace – but it’s the first time I can remember Directions to Disconnect (batteries, or perhaps anything) for System Strength. So am noting MN144415 issued at 23:30 on Sunday 5th July 2026 for future reference:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 05/07/2026 23:30:20
——————————————————————-
Notice ID : 144415
Notice Type ID : MARKET INTERVENTION
Notice Type Description : Reserve Contract / Direction / Instruction
Issue Date : 05/07/2026
External Reference : Direction – NSW region to Transgrid to disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE
Direction – NSW region to Transgrid to disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery
Refer to Market Notice 144416
In accordance with section 116 of the National Electricity Law AEMO is issuing a direction to Transgrid. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: Transgrid at 2325 hrs 05/07/2026
Required actions: Disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery from the network at 2327 hrs 05/07/2026
Services provided: N/A
Circumstances necessitating the Direction:System Strength
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: until further notice.
Transgrid does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-’
Note that this was only a temporary measure, and was cancelled via MN144418 ~ 90 minutes later:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 06/07/2026 00:59:21
——————————————————————-
Notice ID : 144418
Notice Type ID : MARKET INTERVENTION
Notice Type Description : Reserve Contract / Direction / Instruction
Issue Date : 06/07/2026
External Reference : Cancellation: Direction issued to: Transgrid to disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE
Cancellation: Direction issued to: Transgrid to disconnect Darlington Point Battery, Riverina 1 Battery, and Riverina 2 Battery
Refer to Market Notice 144415
Direction is cancelled from: 0100 hrs 06/07/2026
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-’
Interestingly, though, we see (via the ‘Bids & Offers’ widget in ez2view) that, through until 04:00 this morning (Monday 6th July 2026 – the the end of the ‘next day public’ data set) there had been no further rebids to return the batteries to service:
… not sure why?

This is really interesting. The three BESSs are using grid forming technology with a contract with Transgrid to provide system strength in that region. And they were directed to disconnect due to system strength.
…..especially when BESS is touted as the darling ‘System Strength King’