Origin Energy drops Minimum Generation levels at Eraring Power Station to 180MW
Some news articles this morning, following a media tour of Eraring Power Station, prompted a piece of quick analysis (focused on ER01) of MinGen levels.
Read MoreA growing list of articles written here on WattClarity that pertain to the planned closure of Eraring Power Station, which was:
1) Initially planned for WHEN
2) Then moved up the schedule to ‘as early as 2025’
3) But subject to considerable speculation prior to that point.
Some news articles this morning, following a media tour of Eraring Power Station, prompted a piece of quick analysis (focused on ER01) of MinGen levels.
Read MoreIn this third excerpt from GenInsights Quarterly Updates for 2024 Q2, we share some perspectives about the amount of Firming Capacity projected to be delivered in net terms, to 2028 (given some withdrawals and some additions).
Reaching for the same NEMreview query we’ve used a few times in 2024 Q2, we take a look at how futures prices have traded in NSW, following the announcement of agreement to extend the service life at Eraring Power Station.
A short follow-on article to this morning’s (about the notice of extension to service for Eraring Power Station) reflecting the update of AEMO data.
Thursday morning 23rd May 2024 saw a media News Conference and announcement that Eraring closure will be delayed until August 2027 … or possibly as far out as August 2029.
It’s Tuesday 21st May 2024 and the AEMO has published an update to the 2023 ESOO … about 8 months since the publication of the prior release, and 4 months before the 2024 ESOO. Some implications for the anticipated closure of Eraring?
Following a reminder in a phone call today, I’ve updated the date range in a NEMreview trend previously used in February to look at percentage of Underlying Demand in NSW supplied for each half hour over the 5 day period Monday 6th May 2024 to Friday 10th May 2024 (which includes 3 volatile periods leading to Administered Pricing).
Today (Wed 15th May 2024) Bruce Mountain writes an opinion piece in the Australian about the recent run of Administered Pricing in NSW, and what it means for the looming closure of Eraring and the energy transition.
On Tuesday 30th April 2024 we reported of rumours about possible extension to Eraring Power Stations. In the 8 days that have followed since that update several things have happened. In this article we provide an update.
Given that we’ve taken an interest in what’s going to happen with the looming closure of Eraring Power Station, I thought it would be useful to our readers to highlight Peter Hannam’s article in the Guardian today about a (possibly soon) decision about an extension to service.
It’s Monday 8th April, the two Eraring units that tripped last week are back online – and I wonder what the cause of the coincident trip was?
With GenInsights Quarterly Update for 2023 Q4 completed, and some time till the end of 2024 Q1, we’ve looked back at Tuesday 14th November 2023 (when AEMO had concerns about low System Strength in NSW) and looked at the level of inertia actually seen in the grid. A useful Case Study to say ‘what would have happened without Eraring?’
Worth noting these three recent news articles from the past 8 days, all pertaining to the slated closure of the Eraring Power Station as early as 19th August 2025 (under 18 months away), but reporting different perspectives.
Last article (on the day) about Thu 29th Feb 2024. Prompted by an AFR article just over 24 hours ago, how large was the contribution of Eraring Power Station to the NSW electricity region today?
A short article to note another view (this one from Clean Energy Finance) on whether Eraring can close in 2025.
Tristan Edis from Green Energy Trading discusses whether a surge in renewable energy projects and battery capacity would be sufficient to fill any reliability gap before (and after) Eraring’s scheduled closure.
The Media Release from the NSW Department of Energy on 22nd November 2023 noting 1,075MW of new firming capacity in NSW – targeting operational date of December 2025.
Yesterday (Wed 18th Oct 2023) Origin Energy held its Annual General Meeting, with discussion wide-ranging. Here’s two things that jumped out to me about the Eraring Power Station, which is currently slated to close in 2025.
The results of the recent MTPASA (Medium-Term Projected Assessment of System Adequacy), published on 17 October 2023, led a declaration of low reserve conditions in Market Notice 110284.
A quick note about Eraring Power Station, with the NSW state budget released today (Tue 19th Sept 2023).