Loy Yang A4 commences return to service ~26 hours after trip on Tue 13th Feb 2024
The third (of 4) units at Loy Yang A that tripped on Wed 13th Feb 2024 is beginning to return to service ~26 hours afterwards.
The third (of 4) units at Loy Yang A that tripped on Wed 13th Feb 2024 is beginning to return to service ~26 hours afterwards.
A follow up on the (bumpy) return to service for Loy Yang A2
The start of a return to service for Loy Yang A3.
Millmerran 1 came back online Wednesday morning 31st January 2024, as per the outage schedule.
Tarong unit 2 came back online late Thursday evening 1st February 2024 … a week earlier than noted in the outage schedule when it came offline.
As December 2023 draws to a close, we take another look at return-to-service expectations for Callide C3 (a couple more weeks) and then Callide C4 (a few more months). References Nick Evans’ interesting articles.
A quick article, following a social media update by CS Energy on the repair process for the cooling towers at Callide C.
A quick note on WattClarity to tie in an update (earlier this month) from CS Energy on the rebuild of the cooling tower for Callide C3 and C4.
More updates recently about the Callide C power station. Looks like we’ll be waiting a while longer for the (delayed again) return to service…
A short article today noting the additional delays in return-to-service expectations for both Callide C3 and C4.
News of the arrival of another high cost replacement component (generator stator) at Callide C4 prompts me to have an updated look … with a new feature in ez2view.
Yesterday (Wed 28th Dec) CS Energy informed the market of further delays in RTS for Callide C3 and C4 – today we take a quick look.
CS Energy’s Kogan Creek restarted on the morning of Tuesday 20th December 2022.
A quick note to echo the news from CS Energy that the replacement generator transformer is onsite.
On Saturday evening 19th November 2022 the Heywood interconnector returned to service following temporary repairs to the tower damaged on Saturday 12th November.
Alerted via an ABC news article, we take a quick look at Callide C3.
Prompted by a comment by a WattClarity reader, I’ve taken a quick look at Loy Yang A2 for the past week.
Third article today about major outages – this one looking at current expectations for RTS for Loy Yang A2 after some apparent slippage.
Spurred by the extended outage at Kogan Creek, we also take a quick look at current expectations for Callide C4.
One of many articles in the AFR this week flagged an extension of major outage on Kogan Creek Power Station. In this article we take a quick initial look.