However overnight there was a hiccup during which it tripped again (for reasons I have not investigated) – as shown in the ez2view snapshot at 10:00 (NEM time) on Wednesday 14th February 2024, this unit is back online again in the early hours of this morning:
Have not seen any generation at LYA1 or LYA4 yet … but thankfully no change in the MT PASA DUID Availability data in the ‘Generator Outages’ widget highlighted above.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
Third article in a series, following the turbine failure at one of the Berrybank Wind Farms (was it Berrybank 2?) … to note that Berrybank 1 has restarted on Friday 7th February 2025.
Following the notice from AGL Energy on Friday last week about the extended outage occurring at Loy Yang A unit 2, here’s some initial thoughts via WattClarity (with more to come as time permits)
Following several different warnings of high temperatures forecast for the lead-in to Tuesday 26th January 2021 (whatever you want to call that day) I’ve taken a quick look at what it’s currently forecast to mean for the NEM…
Be the first to commenton "Hiccup in return to service of Loy Yang A2"