However overnight there was a hiccup during which it tripped again (for reasons I have not investigated) – as shown in the ez2view snapshot at 10:00 (NEM time) on Wednesday 14th February 2024, this unit is back online again in the early hours of this morning:
Have not seen any generation at LYA1 or LYA4 yet … but thankfully no change in the MT PASA DUID Availability data in the ‘Generator Outages’ widget highlighted above.
One of three founders of Global-Roam back in 2000, Paul has been CEO of the company since that time.
As an author on WattClarity, Paul's focus has been to help make the electricity market more understandable.
An article in the Australian this morning alerted me to yesterday’s Federal Court ruling against AGL Energy for not supplying contingency FCAS services (from Bayswater and Loy Yang A) when enabled by NEMDE. Here’s a quick look…
The ongoing (second) outage at Loy Yang A unit 2 is a timely reminder of the need to progress the 2 rule change proposals submitted by ERM Power with respect to MT PASA data duration, and granularity.