On Thursday 1st October 2026, Project Energy Connect went live in AEMO Market Systems:
… we reported some of this via ‘Project Energy Connect goes live today (Thursday 1st October 2026)’.
So it’s worth noting that AEMO published MN145449 at 12:37 on Friday 2nd October 2026 to report on other developments on the other main link into South Australia:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 02/10/2026 12:37:05
——————————————————————-
Notice ID : 145449
Notice Type ID : GENERAL NOTICE
Notice Type Description : Subjects not covered in specific notices
Issue Date : 02/10/2026
External Reference : Release of Heywood limit from SA to Victoria – 2nd October 2026
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE
Refer to market notice 144186.
AEMO, Transgrid and Electranet have reviewed the test results following the Heywood testing on 2nd June 2026. The next hold point can now be released.
The hold point of 600 MW from SA to Victoria will be implemented at 1400 hrs 2nd October 2026. The following constraint set will be invoked:
I-SV_600_TEST
Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link: https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic—final-test-program.pdf?la=en.
Ben Blake
AEMO Operations
——————————————————————-
END OF REPORT
——————————————————————-

Be the first to comment on "AEMO notes ‘Release of Heywood limit from SA to Victoria’ on Friday 2nd October 2026"