Project Energy Connect goes live today (Thursday 1st October 2026)

Today is Thursday 1st October 2026 which means that there are a number of milestones achieved today with respect to the NEM – including the following:

Our focus today will be on PEC Stage 2.

 

A reminder of the basics

For those:

  • who’d like a refresher on the high level concepts;
  • but who are not so inclined to delve into the gorier details of loop flows, TAP settings, and associated constraint equations etc …

… we wrote an article for you earlier in ‘The *basics* of how Project Energy Connect will appear in NEM Data’:

2026-05-18-WattClarity-TheBasicsOfPEC

 

 

 

In the market data

In what follows, we might evolve this article to highlight some things as they progressively reveal themselves:

 

 

Prior to today …

We’ve already written a number of articles about Project Energy Connect (collated here).  Here are a couple in recent days flagging the progressive entry

 

A week ago, in ST PASA

Linton wrote last Thursday 24th September 2026 about ‘PEC Stage 2 enters the ST timeframe’.

 

Tuesday afternoon and Wednesday afternoon … in P30 Predispatch Data

We wrote yesterday about ‘PEC Stage 2 appearing in predispatch’.

 

 

 

 

Today

Already today we have seen some action:

 

Midnight, beginning Thursday 1st October 2026

This morning the interconnector was registered in AEMO’s Market Systems – as noted by AEMO in MN145435:

‘——————————————————————-
MARKET NOTICE
——————————————————————-

From :              AEMO
To   :              NEMITWEB1
Creation Date :     01/10/2026     00:00:28

——————————————————————-

Notice ID               :         145435
Notice Type ID          :         GENERAL NOTICE
Notice Type Description :         Subjects not covered in specific notices
Issue Date              :         01/10/2026
External Reference      :         NSW to SA (Project Energy Connect) Interconnector Registered – 01/10/2026

——————————————————————-

Reason :

AEMO ELECTRICITY MARKET NOTICE

The New South Wales to South Australia (Project Energy Connect) interconnector has been registered in AEMO’s market systems with effect from 00:00 hrs AEST on 1 October 2026. The ID of this interconnector is NSW1-SA1.

The capacity of this interconnector is +/- 150 MW. Currently the line 6F (Bundey to Buronga) is out of service – this is planned to return to service at 1200hrs 1 October. Refer to NOS for updates for this outage. When the line is returned to service the loop flow constraints will be active in the set L-PEC_X_6C_6G_6H.

For more information refer to the PEC project page on AEMO’s website:

Go live plan:

https://www.aemo.com.au/-/media/files/initiatives/project-energyconnect/implementation-toolbox/pec-mi-final-industry-go-live-plan

PEC project webpage:

https://www.aemo.com.au/initiatives/major-programs/nem-reform-program/nem-reform-program-initiatives

Manager NEM Real Time Operations

——————————————————————-
END OF REPORT
——————————————————————-’

Here’s a snapshot of the ‘Interconnector Dashboard’ widget in ez2view, time travelled back to 00:05 (NEM time) … being the first Dispatch Interval in the calendar day after the interconnector has been registered:

2026-10-01-at-00-05-ez2view-Interconnector-PEC

Note the constraint equations:

1)  limiting both Export Limit and Import Limit to 0MW

2)  with (at this time) flows not expected until the half-hour period ending 12:30 in the P30 predispatch run … aligned with the planned return-to-service of line 6F (Bundey to Buronga), flagged in the Market Notice above.

 

 

 

Action pushed back 30 minutes (at ~11:50) …

Per the earlier P30 predispatch runs (such as noted above, notwithstanding Tripwire #1 (which itself has a 5-year anniversary today)) I’d been interpreting to suggest that we might see flows start from the 12:05 Dispatch Interval.

But, as captured in this ‘Forecast Convergence’ widget snapshot, we see that from ~11:50:40 (when P5 predispatch data was published for 11:55 and beyond) we see a 30-minute delay to ‘action happening’ was rolled through the AEMO data sets.

2026-10-01-at-12-10-ez2view-Interconnector-PEC

In this image, we see no flows until 12:35 (NEM time).

 

 

 

Metered Flows start, from 12:15 …

In this collage of 3 x ez2view widgets (including the ‘Interconnector Dashboard’ widget) at 12:35, we see both:

1)  That Export Limit (and hence Target Flow) remains at 0MW

2)  But that Metered Flow has started earlier … with the first non-zero flow captured at 12:15 (i.e. SCADA snapshot at the end of the 12:15 Dispatch Interval).

2026-10-01-at-12-35-ez2view-Interconnector-PEC

 

 

Target Flows start from 12:35

The first non-zero Export Limit and NSW1-SA1, and hence Target Flow, occurred for the 12:35 Dispatch Interval.

… but I’ve chosen to use this snapshot from NEMwatch v10.4* for the 12:40 Dispatch Interval to illustrate both:

* NEMwatch v10.4 was the upgrade released in July 2026 in preparation for PEC Stage 2.

1)  The flow west; and also

2)  A narrowing of the price gap between NSW and SA

2026-10-01-at-12-45-NEMwatch-with-PEC-flowing

 

 

Bringing NSW and SA prices together

Just over 2 hours later (at the 14:50 Dispatch Interval ) we clearly see the effect that PEC Stage 2 has had on bringing NSW and SA prices more closely* together – via this NEMwatch snapshot:

* remembering that ‘more closely together’ does not necessarily equate to ‘lower’ for one region in that particular dispatch interval … although the theory is that spot prices will be lower in the long run as a result:
(a)  notwithstanding the cost of transmission
(b)  and changing participant behaviours (short term and long term),
(c)  etc…

2026-10-01-at-14-50-NEMwatch-with-PEC-flowing

 

More to come?

… perhaps


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

Be the first to comment on "Project Energy Connect goes live today (Thursday 1st October 2026)"

Leave a comment

Your email address will not be published.


*