Over the weekend we noticed that Giles Parkinson had written ‘One of Australia’s biggest wind farms forced to revisit off-take deals after lengthy construction delays and repairs’ with respect to Acciona’s MacIntyre Wind Farm … with the following jumping out:
‘The Macintyre wind farm, in Queensland’s south-east, was originally due to be completed in late 2024, but ran into issues early in its development and was then forced to replace equipment on dozens of its Nordex turbines after a turbine blade break in December, 2024. It is now not expected to be complete until mid 2027.
The project – majority owned by Spain’s Acciona Energía – was originally sized at more than one gigawatt – which would have made it the first in the country to reach that scale.
But it was downsized to 930 MW after the government owned CleanCo dropped plans for a 103 MW facility within its precinct.’
Curiosity struck, so we took a quick look at the long-term trend of high-level operational statistics with the ‘Trends Engine’ within ez2view:
With respect to the chart above, a few key dates:
1) It was 12th August 2024 when the unit MCINTRY1 was registered with a Maximum Capacity* of 890MW in the AEMO market systems:
(a) that was approaching 26 months ago now;
(b) for those readers noting an apparent inconsistency between the two numbers for capacity:
i. please firstly re-read ‘Analytical Challenge – choosing what measure to use, for ‘Installed Capacity’’ as a reminder;
ii. and note that:
> we will mostly (but not always) refer to Maximum Capacity here (only 890MW), given it sets a maximum output onto the AC grid;
> whereas others at times (and us infrequently) might refer to Registered Capacity (923.4MW), which can be different (and which is presumably what Giles has rounded up to be 930MW).
2) It was 29th August 2024 when the first glimmer of output was seen
3) Just last week (Monday 28th September 2026) was when the unit’s peak availability and output to date:
(a) availability (666MW) and output (641MW)
(b) but that’s an availability factor of only 75% of the capacity of the station, at this point.
Utilising the ez2view installed software and utilising the ‘Unit Dashboard’ widget, we see the peak output (641MW being FinalMW for 19:30 NEM time) on Monday evening 28th September 2026:
Next, we see (via the ‘Constraint Dashboard’ widget focused on the ‘#MCINTYR1_E1’ constraint equation) as follows:
From this we see:
1) at 19:30 the Hold Point was only 632MW
… albeit:
(a) the Semi-Dispatch Cap was not set for 19:30 because the UIGF from AWEFS was only 600MW;
(b) allowing the unit to output freely … meaning output of 641MW meant a Dispatch Error of –41MW (over-performance).
2) but the Hold Point was coincidentally upped to 670MW from 21:50 on Monday evening 28th September 2026.
Finally, with a longer-term view via the ‘Constraint Sets Gantt’ widget, we see (looking back a year):
I’ve highlighted:
1) the long-running invocation of the ‘#MCINTYR1_E’ constraint set over the past year (which just contains the single ‘#MCINTYR1_E1’ constraint equation), which is the means by which AEMO has been maintaining ‘hold points’ on the unit;
2) and that:
(a) this range of invocation has
(b) with these being:
i. Most recently, on Sunday evening 28th September 2026 (i.e. to 670MW)
ii. On 18th August 2026 (i.e. to 632MW)
iii. On 4th june 2026 (to 531MW)
iv. On 19th December 2025
v. On 10th July 2025
… and so on backwards in time.