Whilst we have the ‘Bids & Offers’ widget in ez2view out and looking at Firming Capacity (a.l.a. the Nelson Review terminology), we take a quick look at Kurri Kurri peaker and see that the testing might commence again tomorrow (Saturday 18th July 2026):
About the Author
Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
Related Articles
Paul McArdle Mon 8th June 2026
More delays in the commissioning process for the Hunter GT (a.k.a Kurri Kurri)
Todays article in the AFR by Angela MacDonald-Smith prompts an updated look at Kurri Kurri GT.
Paul McArdle Wed 27th May 2026
Both units at Hunter GT get a test run
It’s Wednesday 27th May 2026 and this is a short note to record that both units at the much-delayed Hunter GT (a.k.a. Kurri Kurri Peaker) have gained a test run in the past couple days.
Paul McArdle Fri 26th June 2026
Hunter GT (a.k.a. Kurri Kurri) now not expected till 1st September 2026
The expected operations date for both units at Hunter GT has been pushed back until 1st September 2026.
Paul McArdle Tue 7th July 2026
Hunter GT gets another test run, across both units … but perhaps on gas, before diesel testing this coming Friday?
Some ez2view alerts triggered last Friday (3rd July 2026) and last night (6th July 2026) to signal that Hunter GT gained a test run … but Snowy Hydro media says testing on diesel starts this Friday (10th July 2026).