Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
An email alert from NEMwatch (noting Scheduled Demand under 500MW in South Australia today) distracts us, and prompts us to dig a little deeper at the longer-term trend.
A quick record of Tamar Valley CCGT coming offline yesterday (Tue 23rd July 2024) after 40 days of solid operations through a low-rain and low-wind winter in Tasmania.
Hot on the heels of a new low point for Operational Demand in South Australia on the weekend, this evening AEMO warns of an ‘elevated risk of contingent disconnection of Distributed PV’ tomorrow (Wed 19th Oct 2022).