Semi-Scheduled Bid MaxAvail – Initial Results
A week’s worth of data provides indications of how semi-scheduled generators are using bid MaxAvail to manage dispatch availability.
A week’s worth of data provides indications of how semi-scheduled generators are using bid MaxAvail to manage dispatch availability.
It is indispensable to understand how the semi-scheduled unit availability gets produced to optimally manage the critical inputs and comprehend dispatch outcomes. This article explains the key inputs and processes, focusing on the dispatch timeframe.
The change to use MaxAvail from the energy bid, for semi-scheduled units, was implemented on 7 August 2023.
2 x AEMO Market Notices this afternoon prompt this article about four upcoming Market Enhancements … with the first to planned to commence from next Monday 7th August 2023
AEMO is re-enabling the ‘MaxAvail’ figure in bids for Semi-Scheduled units. It will act as a limit on capacity available, feeding into the NEMDE dispatch process for the unit. We look at how Semi-Scheduled plant have currently been treating MaxAvail in the bid and share some insights.
Today (Tue 23rd May) is the go-live date for AEMO’s EMMS v5.2 – which will contain new data for some market enhancements. Here’s a quick look at where this first change will appear in ez2view, highlighting some considerations for Semi-Scheduled units and self-forecasting.
Alerted by RenewEconomy on social media that Beryl Solar Farm was offline due to bushfires, I used ez2view to take a quick look.