On Tuesday last week Linton wrote about ‘Basslink on track to operate as regulated interconnector from 1 July 2026’.
In part because we might want to refer directly to it later, we’ll note that at 23:58 at the tail end of yesterday (Tuesday 30th June 2026) the AEMO published MN144280 as follows:
‘——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 30/06/2026 23:58:12
——————————————————————-
Notice ID : 144280
Notice Type ID : GENERAL NOTICE
Notice Type Description : Subjects not covered in specific notices
Issue Date : 30/06/2026
External Reference : Network Service Provider Classification Update – Basslink
——————————————————————-
Reason :
AEMO advises NEM Participants that:
Basslink Pty Ltd has transitioned its network service classification from a Market Network Service Provider (MNSP) to a Transmission Network Service Provider (TNSP) with effect from 00:00 hrs AEST on 1 July 2026.
This change follows the Australian Energy Regulator (AER) determination that Basslink network services are to be treated as prescribed transmission services under the National Electricity Rules (NER).
For more information refer to the following links:
Basslink Final Industry Go-live Plan: https://www.aemo.com.au/-/media/files/initiatives/nem-reform-program-initiatives/basslink-determination-participant-support-arrangements/basslink-final-industry-go-live-plan.pdf
Basslink project webpage: https://www.aemo.com.au/initiatives/major-programs/nem-reform-program/nem-reform-program-initiatives/basslink-determination-participant-support-arrangements
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-‘
For those watching on at work (or at home), it’s been a slow start in terms of flows (because of the ‘I-BL_ZERO’ constraint set).

Be the first to comment on "AEMO notes ‘Network Service Provider Classification Update – Basslink’"