The long goodbye continues as Eraring’s closure officially extended until 2029

Origin Energy has this morning announced that the operating life of Eraring Power Station, previously scheduled to close in 2027, will be formally extended by a further two years.

This outcome was stated as a possibility when the previous two-year extension was announced in May 2024, and has been widely anticipated following market commentary and indications from Origin as recently as August last year. Our broader coverage of the long-running Eraring closure timeline can be found on this section of our blog.

In the official statement, Origin stated:

Origin Energy Limited (Origin) has advised the Australian Energy Market Operator (AEMO) that it will extend the operation of all four units of the Eraring Power Station from 19 August 2027 to 30 April 2029, to support energy supply in NSW through the energy transition.

Extending Eraring’s operation reduces risks to system security highlighted by AEMO in its recently released Transition Plan for System Security and enables the plant to continue to support reliable power to NSW households and businesses.

Origin CEO Frank Calabria said, “We’ve taken the decision to extend Eraring’s operations after assessing a range of factors, including the needs of our customers, market conditions and the important role the plant plays in the NSW energy system.

“Good progress is being made on the delivery of new energy infrastructure including major transmission works and projects like our large-scale battery at Eraring, but it has become clear Eraring Power Station will need to run for longer to support secure and stable power supply.

Our decision to keep Eraring operating until April 2029 provides more time for renewables, storage and transmission projects to be delivered, and reflects uncertainty regarding the reliability of Australia’s aging coal and gas fleet. 

We are pleased to provide greater certainty for the community, our people and the market about Eraring’s future, and I want to commend the professionalism and focus of the Eraring team in continuing to maintain and operate the plant reliably given the vital role it continues to play for energy users in NSW,” Mr Calabria said.

The full media release from the company can be found here.

The screenshot from our ez2view software below shows that this extension is now reflected in the AEMO’s MTPASA dataset, with an additional 2,880 MW of coal availability in NSW from the 19th of August 2027 compared with what the MTPASA projections were showing yesterday.

 

At 10:19 NEM time, the AEMO issued a market notice stating that they intended to rerun the MT PASA process out-of-cycle to incorporate Eraring’s announced extension:

 

MARKET NOTICE 132984
________________________________________________________________________________________________

Notice ID 132984
Notice Type ID LRC/LOR1/LOR2/LOR3
Notice Type Description MARKET
Issue Date Tuesday, 20 January 2026
External Reference RESERVE NOTICE MT PASA 19 January 2026
________________________________________________________________________________________________

The MTPASA results published on 19 January 2026 identify annual unserved energy exceeding the Reliability Standard between:
-- January 2027 - January 2028 in New South Wales.

AEMO declares Low Reserve Conditions in accordance with clause 4.8.4 of the National Electricity Rules for the following region(s) and period(s):
-- August 2027 to November 2027, and January 2028 in New South Wales
when forecast demand exceeds supply under some circumstances.

This MT PASA run was completed on 19 January 2026 and reflects MT PASA offer submissions available at the time of the run. The assessment does not include the extension of the Eraring Power Station retirement date to 30 April 2029, which was announced on 20 January 2026.

AEMO intends to undertake an out-of-cycle MT PASA run to incorporate the Eraring Power Station retirement date extension and will publish updated results as soon as practicable.

MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any AEMO intervention.

For further information on MT PASA, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/reliability-standard-implementation-guidelines.

This notice supersedes Market Notice 132721 published on 13 January 2025.

Forecasting

AEMO

Update: At 16:21 NEM time on Tuesday afternoon, the AEMO issued another market notice related to the previous notice posted above, which stated that the new MT PASA run had been completed and the result identified that two periods of projected unserved energy (above the reliability standard) in 2027 and early 2028, were no longer identified.

 

MARKET NOTICE 133036
________________________________________________________________________________________________

Notice ID 133036
Notice Type ID LRC/LOR1/LOR2/LOR3
Notice Type Description MARKET
Issue Date Wednesday, 21 January 2026
External Reference RESERVE NOTICE MT PASA 21 January 2026
________________________________________________________________________________________________

AEMO published an out-of-cycle MT PASA run on 21 January 2026 following the announcement on 20 January 2026 that the Eraring Power Station retirement date has been extended to 30 April 2029. The result identifies no Low Reserve Conditions.

Low Reserve Conditions previously identified in:
-- August 2027 to November 2027, and January 2028 in New South Wales
are no longer identified, as unserved energy is no longer forecast above the Reliability Standard in this region during these periods.

MTPASA informs the market of potential reliability issues to allow the market to respond in the first in-stance, potentially avoiding the need for any AEMO intervention.

For further information on MT PASA, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy.

For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/reliability-standard-implementation-guidelines.

This notice supersedes Market Notice 132984 published on 20 January 2026.

Forecasting

AEMO

 

Media Coverage

Unsurprisingly, the decision has attracted significant attention across both general and energy-sector media — with some reporting citing reliability and policy considerations, and other pieces criticising Origin’s progress in developing replacement renewable capacity. For readers interested in how the story is being framed elsewhere, we’ve collated a list of articles we’ve spotted below:


About the Author

Dan Lee
Dan is a Market Analyst, who joined Global-Roam in June 2013. He departed (and returned) for a couple of brief stints overseas, before rejoining the team permanently in late 2019. Alongside his work at Global-Roam, he has undertaken short-term contract roles as an analyst and researcher in various areas of the energy sector. Dan graduated from the Master of Sustainable Energy program at the University of Queensland in 2024.