RERT dispatched on 27 November 2024 in NSW

With the benefit of the public next-day data we observe that RERT was indeed activated and dispatched for the hour encompassing dispatch intervals 15:50 to 16:45.

Earlier reporting on the day observed:

  1. The commencement of RERT negotiations, followed by
  2. A market notice indicating that RERT had been activated/dispatched, and
  3. The market notice announcing the end to the RERT intervention.

The following chart summarises the magnitude and timing of RERT dispatched.

  • The top panel shows the magnitude relative (by subtraction) to market demand changes (TOTALDDEMAND in the MMS) at the time.
  • The lower panel confirms that the 65 MW level was constant throughout the period.


About the Author

Linton Corbet
Linton is a Senior Software Engineer and Market Analyst, who joined Global-Roam in August 2020. Before joining the company, Linton worked at the Australian Energy Market Operator (AEMO) for seven years, including four years as an analyst within their demand forecasting team. Before entering the energy sector, he worked as an air quality scientist in the Czech Republic.