Home > Headline Events > 2021 – 11th June – flooding at Yallourn mine
Posted by Paul McArdle
Friday, July 2 2021
Topic: 2021 – 11th June – flooding at Yallourn mine , Winter 2021 in the NEM
In our recap of pricing patterns through Q2 2021 this morning I noted that Yallourn 4 had been anticipated to be back on Wednesday 30th, but had missed that date.
Turns out that the unit commenced operations this evening – 17:20 on Friday 2nd July 2021, as shown in this snapshot from ez2view just now:
At the time I am posting this, there’s no further update on the EnergyAustralia news site since the Tuesday 29th June update I referenced here :
One of three founders of Global-Roam back in 2000, Paul has been CEO of the company since that time.
As an author on WattClarity, Paul's focus has been to help make the electricity market more understandable.
Related Articles
Paul McArdle
Saturday, September 14 2024
On Sunday 8th September 2024 the Herald Sun published an article speculating about possible Service Life extension to Yallourn Power Station.
Paul McArdle
Tuesday, July 6 2021
A short record of gas prices being up at $20/GJ and above through a cold spell for winter, with other factors at work.
Paul McArdle
Wednesday, November 13 2024
Partly prompted by a comment yesterday from a WattClarity reader (Liam), and powered by ‘next day public’ data, we take a look at Yallourn Power Station on Tuesday 12th November 2024.
Paul McArdle
Tuesday, May 30 2023
More updates recently about the Callide C power station. Looks like we’ll be waiting a while longer for the (delayed again) return to service…