Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
A quick record of Tamar Valley CCGT coming offline yesterday (Tue 23rd July 2024) after 40 days of solid operations through a low-rain and low-wind winter in Tasmania.
On Wednesday 17th July 2024, CS Energy released the Brady-Heywood report (about Callide C4 failure on 25th May 2021) and the HartzEPM Report (about CallideC3 failure on 31st Oct 2022) ... and an Action...
In the last MT PASA DUID Availability data update for Friday 12th July 2024 the return to service expectation for the repaired Callide C4 unit has been delayed again another 40 days ... now...
A quick look at forecast 'Market Demand' and NEM-wide IRPM for next week ... with Ben Domensino writing about a 'Ferocious Tasman Low to hit southeast Australia next week'
Taking the ‘worm line’ cumulative trend recent Q2 periods (used for wind, hydro and gas-fired power), we now apply this to coal-fired generation during 2024 Q2.
Taking the ‘worm line’ cumulative trend recent Q2 periods (used for wind and then hydro), we now apply this to gas-fired generation during 2024 Q2. We see two distinctly different patterns ... early in...
CS Energy has released the latest draft of the ‘Brady Report’ - a draft Executive Summary, a draft Part A (Technical) and a draft Part B (Organisational)
A quick look at the ‘N-DPWG_63_X5’ constraint set as a driver for the curtailment of solar (and other) units in south-western NSW on Monday 24th June 2024.
Taking the ‘worm line’ cumulative trend recent Q2 periods (first used for wind), we now apply this to hydro during 2024 Q2 to see to what extent hydro production volumes are lower than recent...
Extending the 'worm line' cumulative trend of wind production through 2024 Q2 (to 22nd June) and comparing to 2023, 2022, 2021 and 2020 reveals a picture that is, at the same time, both frightening...
On Friday 21st June 2024 the unit 2 of Barron Gorge hydro facility has started up - the next step in a repair process following TC Jasper six months ago.