What’s happening in ~2 weeks, with respect to development and commissioning at Kidston Pumped Hydro (or associated network)?

This article was drafted yesterday (on Tuesday 18th August 2026) but did not get time to publish.  Rather than rework with updated screenshots, publishing now – so keep in mind.

—

I was in a conversation with a new ez2view client earlier today and I noticed something in a filtered list of constraint sets that I thought might be of interest to our readers.

Using a different form of a Constraint Set filter, that reaches inside the constraint equations within them to look for units starting with ‘KIDS*’ (i.e. representing Kidston Pumped Hydro) I noted one set of 4 x zero output constraint sets with a scheduled invocation only out until 12:00 on Wednesday 2nd September 2026:

2026-08-18-at-13-15-ez2view-ConstraintSets-Kidston

Now, the removal of these ‘zero output constraints’:

  • would be a precursor to any output from these units
  • but does not necessarily mean that the unit would be providing output (or, more likely, pumping uphill to charge the upper pond) at that time.

… but, at least for me, that was an interesting development:

  • that I noted on the call.
  • and which prompted me to delve further here…

 

Now, Genex Power was taken private (by J-Power) some time ago, so there is no need for the company to issue ASX status updates and the like … :

 

However, before we get our hopes up … it’s worth a reminder that on 1st May 2026 we noted ‘Delays at Kidston Pumped Hydro (operations not expected till July 2027)?’:

2026-05-01-WattClarity-Delays-at-Kidston

 

Still slated for 22nd July 2027

Given that this earlier article used the ‘Forecast Convergence’ widget in ez2view to look at the Kidston Pumped Hydro (generation side) units (i.e. *G1 and *G2) we provide an updated view below:

2026-08-18-at-13-35-ez2view-ForecastConvergence-Kidston-Gen

Headline is that it’s still around 22nd July 2027 where the availability of the generation-side units is slated to be non-zero.

Indeed, a reference to the first image above (of the ‘Constraint Sets’ widget) reveals, in the gold colour, another set of ‘zero output’ constraints sets:

  • these are the ‘hold point constraints’
  • they currently have an indefinite end time, but this will be adjusted (sometime after July 2027, presumably) when the unit is ready to commence commissioning.

 

So, in summary:

  • we’ll still have to wait another ~12 months to see any real action in the market data.
  • but the change in those 4 x constraint sets on or around Wednesday 2nd September 2026 is a curiosity.

About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.