Revisiting the CIS-awarded project pipeline, ahead of the ESOO 2026

A bit over a year ago we began our research into what became a four-part analysis series examining the federal government’s flagship energy policy — the Capacity Investment Scheme (CIS) — with the aim of understanding how the scheme was tracking so far. At that point, sentiment towards the policy was still broadly supportive and optimistic, though some pointed questions were starting to be asked.

The mood surrounding the scheme has shifted a long way in the past year, and in recent months we’ve been seeing more honest critiques of the scheme from all across the media spectrum (including RenewEconomy and the AFR).

With the AEMO due to release the 2026 Electricity Statement of Opportunities (ESOO) next week, and lingering questions about Yallourn’s scheduled closure, in this article we take an updated look at the projects which have been announced as winners for each of the CIS tender rounds. For each round we will look at the timeline of each project’s AEMO Status category — as used for ESOO modelling — against the real-world status implied by company/public announcements.

Tracking project progress round-by-round

Below we will go through each CIS tender round that was open to prospective NEM projects, which means we’ll be looking at Rounds #1, #3, #4, #7 and #8 only.

For each round we’ll start by looking at how projects have been progressing — as per public announcements from involved companies and other official sources. We’ll focus on the following milestones: financial close, start of construction, commissioning and full operations. We’ve collated this data manually, so if you spot any errors in the information we’ve collected, then please leave a comment below or drop us a line.

We’ll then compare this data against how the AEMO has been classifying the status of each of these projects — as published in their Generation Information dataset over time. As a quick refresher, the AEMO has three status categories for development projects: Committed projects have satisfied all five of their commitment criteria (land, contracts, planning, finance and construction). Anticipated projects meet at least three of the five (and are obliged to have submitted a survey update to the AEMO in the previous six months). Proposed projects meet fewer than three, and are excluded from the reliability modelling altogether.

The reason we’ve put together this analysis is because we are interested in any gaps that may appear between the two types of reporting.

As we’ve previously written about, ‘Anticipated’ projects are now included in the modelling for the ESOO’s central reliability forecast — however this wasn’t always the case. Up until the 2023 edition, the central reliability forecast counted only committed development projects. Since the 2023 ESOO, anticipated projects are included which means that meeting three of the five commitment criteria has been enough for a project to contribute within the outlook period — meaning a project need not have broken ground or secured full financing when it begins to contribute to ESOO modelling results.

Tender Round #1

There were 84 initial bids for this round, with 19 eventual ‘winners’ announced on December 11th 2024. The round was a ‘generation’ tender, which means it was open to solar/wind projects (with or without batteries attached), and it had a capacity target of 6 GW. Ultimately, the aggregate total of awarded capacity was 6,375 MW (and 3,562 MWh of storage).

The chart below shows that only one project — the 46 MW Mokoan Solar Farm, the smallest of the round — was already under construction when the winners were revealed, and it remains the only one fully operating today. Goulburn River Solar Farm is a similar case: Lightsource bp states construction began around December 2024, and since DCCEEW names tender winners before contracts are signed, the project likely reached FID independently of the scheme.

A timeline of development for the winning projects from tender round #1.

Source: Company Announcements.

Note: Marker not shown if financial close has not been publicly announced. Please leave a comment below or drop us a line if you spot any errors.

Keeping in mind that ‘winners’ are still subject to contract negotiation and execution, above we can see that a further 3 projects have reached financial close since being announced of having ‘won’ a CIS place. This represents just 574  MW — or 9% — of the capacity awarded in the round.

Those 3 projects are: the Palmer Wind Farm (274 MW, SA) which reached financial close in December 2025 and began construction last month; and Edify Energy’s Ganymirra and Majors Creek solar power stations (150 MW each, QLD) which reached financial close only last week.

Notably, Edify’s two projects reached financial close after co-located later stages of the same project picked up their own CIS agreements in Tender Round #8 in June. Similarly, Goulburn River Solar Farm was boosted by its co-located BESS winning an LTESA contract one year prior.

In the next chart we show how the AEMO has been reporting the status of all of these projects.

AEMO Generation Information status for the winning projects from tender round #1.

Source: AEMO Generation Information.

Although only 5 of the 19 projects have publicly announced that they have reached close — as of the latest update, 6 of the remaining 14 projects are marked as ‘Anticipated’ by AEMO — including two of the largest projects in the round, the 936 MW Valley of the Winds and the 700 MW Sandy Creek Solar Farm.

That last chart also highlights a couple of inconsistencies with the AEMO’s reported data. We can see that movement in these categories is not always forward: with Barwon Solar Farm promoted to ‘Anticipated’ in January 2026 and later dropped back to ‘Proposed’. We can also see examples of the dataset lagging reality with Palmer Wind Farm (which has been under construction since December 2025) still marked as ‘Proposed’ from the AEMO as of last month. Many of these inconsistencies are due to the data being self-reported by project proponents, and on an irregular cadence.

To provide some further context about this round in particular, it’s worth noting that round 1 was impacted by some confusion surrounding whether the CIS would cover network curtailment risk. In Part 3 of our article series last year, we chronicled a late change to the CIS draft pro-forma that removed a clause that implied that network curtailment would be covered under the agreement — with the change to the pro-forma made just as projects were invited to bid their revenue floors for this round. Aidan Morrison from the Centre for Independent Studies (which confusingly, also bears the CIS acronym) made several Freedom of Information requests to uncover internal departmental communication about this last-minute change, which he later published in this X/Twitter thread.

There was also reporting from the AFR in April that several wind projects from this round — purported to include Valley of the Winds and Spicers Creek — were seeking to renegotiate the terms of their CIS agreements due to rising construction costs. Chris Bowen later shut that down in June stating that contracts would not be renegotiated, but proponents are welcome to withdraw and bid again in future tenders.

Tender Round #3

There were 124 bids for this round, with 16 eventual winners announced on September 16th 2025. Round 3 was a ‘dispatchable’ round (but open to co-located/hybrid VRE projects) and was heavily oversubscribed — there were roughly 34 GW / 135 GWh worth of bids chasing a 4 GW / 16 GWh target. All 16 winners were lithium-ion batteries, totalling 4,130 MW and 15,371 MWh.

A timeline of development for the winning projects from tender round #3.

Source: Company Announcements.

Note: Marker not shown if financial close has not been publicly announced. Please leave a comment below or drop us a line if you spot any errors.

4 of the 16 have reached financial close — but 3 of those 4 got there before the round was even awarded. Mornington BESS (240 MW, VIC) had been under construction since October 2024, the Calala BESS (150 MW, NSW) reached FID in March 2025, and Reeves Plains Energy Hub Battery (250 MW, SA) reached FID in July 2025.

That leaves just the Koolunga BESS (200MW) in South Australia which reached financial close last month after reaching an offtake agreement with Gunvor Group (who in turn was providing a firm renewable financial product to data centre company, Firmus).

On a power capacity basis that means 200 MW (or 4.8%) out of 4,130 MW contracted has reached FID since the announcement of winners 11 months ago.

AEMO Generation Information status for the winning projects from tender round #3.

Source: AEMO Generation Information.

In the AEMO’s latest reporting, 6 projects currently have ‘Anticipated’ status, 3 of which were upgraded to this status immediately following the award despite not reaching FID — Teebar, Little River and Joel Joel.

Tender Round #4

There were 84 bids in this ‘generation’ round, with 20 eventual winners announced on October 9th 2025. The round awarded 6,640 MW of generation (plus 11,444 MWh of co-located storage) against a 6 GW target, from a bid pool of roughly 25.6 GW.

A timeline of development for the winning projects from tender round #4.

Source: Company Announcements.

Note: Marker not shown if financial close has not been publicly announced. Please leave a comment below or drop us a line if you spot any errors.

4 projects from the round, totalling 1,128 MW, have reached financial close, and unlike rounds 1 and 3, all four did so after the award. Carmody’s Hill Wind Farm (247 MW, SA) reached financial close in December 2025; Edify’s Guthrie’s Gap and Smoky Creek (300 MW each, QLD) closed together in May 2026; and Lower Wonga Solar Farm (281 MW, QLD) started construction in June (and is assumed to have reached FID in the weeks/months prior).

All four of these projects signed offtake arrangements with either Snowy Hydro or Rio Tinto. Carmody’s Hill signed a long-term PPA with Snowy Hydro in November 2025 and closed the following month. Guthrie’s Gap and Smoky Creek are underpinned by a 20-year hybrid services agreement with Rio Tinto, under which Rio takes 90% of the power and battery capacity to supply its Gladstone aluminium operations. The Lower Wonga Solar Farm also signed a PPA with Rio Tinto shortly before reaching FID.

AEMO Generation Information status for the winning projects from tender round #4.

Source: AEMO Generation Information.

Looking at the AEMO status Gantt chart above we see that all four of those projects have been moved to committed status, but a further 5 are currently sitting as ‘Anticipated’ (representing 1,617 MW of capacity).

Tender Round #7

There were 53 bids for this ‘gerneration’ round, representing 18.6 GW, with 19 eventual winners announced on May 23rd 2026. At 7,827 MW of capacity awarded, it was the largest CIS round to date in this regard. There was a notable focus on wind when the winners were announced, including the three largest single awards in the scheme’s history — Yanco Delta (1,498 MW, NSW), Bungaban (1,150 MW, QLD) and Theodore (1,022 MW, QLD).

A timeline of development for the winning projects from tender round #7.

Source: Company Announcements.

Note: Marker not shown if financial close has not been publicly announced. Please leave a comment below or drop us a line if you spot any errors.

As the winners were only announced less than three months ago, the chart above is understandably empty, with none of these projects publicly announcing financial close or the commencement of construction so far.

AEMO Generation Information status for the winning projects from tender round #7.

Source: AEMO Generation Information.

Despite this, four are ‘Anticipated’ — Bungaban and Gunning were both promoted to Anticipated status in the July update, joining Bullyard and Woolsthorpe.

For additional context, round 7 was also the first NEM tender since DCCEEW made a number of key reforms to the CIS application and contracting process — including a greater focus on ready-to-deliver projects, an unwillingness to accept commercial departures from the CIS agreement pro-forma and an introduction of a ‘reserves list’.

Tender Round #8

There were 73 bids for this ‘dispatchable’ round totalling 76.4 GWh of proposed capacity — nearly five times the 16 GWh target. The 15 eventual winners were announced on June 24th 2026. As with round 3, every winner was a standalone lithium-ion battery, with a total of 4,205 MW and 16,074 MWh of capacity awarded.

One project in round 8 was already under construction when the winners were announced: the Bulabul BESS Stage 1 (300 MW, NSW), formerly known as Wellington BESS, had reached financial close in July 2025 — eleven months before it won its CIS contract.

A timeline of development for the winning projects from tender round #8.

Source: Company Announcements.

Note: Marker not shown if financial close has not been publicly announced. Please leave a comment below or drop us a line if you spot any errors.

Again, as the winners were only announced in June, it is obviously too early to draw conclusions from this round. However we can see below that three projects are already marked as anticipated in the AEMO dataset (including the Ganymirra and Majors Creek BESS — which are co-located but distinct projects from the round 1 projects which reached FID last week).

AEMO Generation Information status for the winning projects from tender round #8.

Source: AEMO Generation Information.

Key Takeaways

Since our initial look almost a year ago, only a handful of additional CIS projects have progressed to FID/financial close — yet a considerably larger number have been promoted to Anticipated status for the purposes of ESOO modelling.

Through the five NEM rounds of the CIS:

  • 89 projects have won a CIS spot (or 29,177 MW of capacity awarded).
  • By our count, of that, only 14 projects (or 3,338 MW of capacity) have reached financial close.
  • Of which, 6 of the 14 projects (or 1,436 MW of capacity) had already got there before they won their spot in the scheme.
  • Leaving just 8 projects (or 1,902 MW of capacity) that have reached financial close since being awarded a CIS place.

These numbers come from our own research of information in the public domain, so may be subject to error. However, they roughly line up with other counts we’ve seen pop up in recent months — including this article by AFR’s Ryan Cropp in July, citing data from Infradebt.

The last two rounds of the CIS were only finalised in the past few months, so those totals above should be read with that in mind. However, the larger point I want to make is that despite those real-world numbers, as of their last update, the AEMO currently have 33 (or 10,436 MW of capacity) of the 89 projects marked as ‘Anticipated’ or higher.

Skimming through our Gantt charts in this article, we can see that 12 projects were upgraded to Anticipated status immediately after their CIS contract award — which may suggest that winning a CIS contract may itself help satisfy AEMO’s ‘contracts’ criterion — which, for a project already holding land and planning approval, can be the third box ticked. So a round award can, by itself, move a meaningful block of capacity into the ESOO central scenario, despite no guarantee of putting a shovel in the ground.

Hopefully this article reminds our readers that with modelling results such as those in the ESOO, it always matters which lens you choose to look through.


About the Author

Dan Lee
Dan is a Market Analyst, who joined Global-Roam in June 2013. He departed (and returned) for a couple of brief stints overseas, before rejoining the team permanently in late 2019. Alongside his work at Global-Roam, he has undertaken short-term contract roles as an analyst and researcher in various areas of the energy sector. Dan graduated from the Master of Sustainable Energy program at the University of Queensland in 2024.

1 Comment on "Revisiting the CIS-awarded project pipeline, ahead of the ESOO 2026"

  1. I would put an asterisk next to Capricorn BESS as that got called in by QLD gov, so it cannot proceed until it gets approvals done again (if it can get approvals again). Junction Rivers has not been granted grid-access to the SW REZ, so also can’t proceed. Moah Ck Wind Farm also had CleanCo pull funding at the direction of QLD gov – it may go ahead, but basically had to start from scratch with financing.

    I would then put a dagger (†) next to any solar project with less than 3hrs battery, and a double dagger (‡) next to any solar farm without a battery. Those projects are very unlikely to get built with current curtailment and midday prices. It gets complicated as many of those projects do have batteries, just not in the CIS.

    The CIS isn’t perfect, but I think the fundamental problem is trying to get private money to build out a grid. Every new generator decreases the profitability of all other generators. It doesn’t matter if you’re building coal/gas/nukes/renewables, you eventually hit a point where it’s not profitable to build more. Also, wind & solar aren’t 1:1 replacements for coal – unless you build mega-projects like Masdar’s 5GW/19GWh solar hybrid (7x larger than Smuthries Greek), but I don’t know if anyone’s willing to make a $8.5b bet on a single project in Australia.