Those alerts triggered a few times in the past 24 hours so, before switching off those particular alerts, I had a quick look via the ‘Bids & Offers’ widget in ez2view and thought some readers might appreciate this snapshot as at 12:55 (NEM time) on Saturday 2nd May 2026:
We can see:
First bid submitted last Friday 24th April 2026, but not used in dispatch until the clock ticked into 00:05 (NEM time) on Tuesday 28th April 2026 (which was when the unit 247MW Maximum Capacity hit the NEMDE systems)
But no output until early this morning (Saturday 2nd May 2026)
And another small burst of availability seen in PD/ST PASA for next Friday 8th May 2026.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
Recent events in the NEM are causing me to wonder whether we’ve suspended logic, and reason, in charting a workable course through this energy transition?
On Wednesday 4th December 2024 we saw that Aaron Kelly of the ABC had written ‘Class action against Queensland’s government-owned electricity generators dismissed’. Today we get a chance to take a first look.
Be the first to commenton "Initial output at Wambo Wind Farm 2 on Saturday 2nd May 2026"
Be the first to comment on "Initial output at Wambo Wind Farm 2 on Saturday 2nd May 2026"