This particular article (however) is belated, and back-dated, and contains a similar filtered snapshot from ‘Bids & Offers’ at 24:00 (NEM time) ending 4th October 2025 focused on the Queanbeyan BESS unit in/around Canberra:
We see, here, the unit come offline on 2nd October 2025 with the ominous rebid reason ‘due to oscillations’.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
At 10:42 (NEM time) this morning the AEMO published MN124235 pertaining to tomorrow (Friday 7th February 2024) for forecast LOR2 in NSW. So we take a quick look…
On Friday 5th December 2025 we also saw EnergyAustralia report to AEMO the 19-day extension to the lengthy unplanned outage at YWPS2 following ‘LP turbine issues’ experienced in August 2025.
Following on from a similar review this time last year, Dan provides an updated look at the economics and performances within the NEM’s big battery fleet, making use of our recently released GSD2024.
A short examination of some of the over-arching factors at play yesterday evening – where prices spiked above $3,000/MWh in all five regions simultaneously.
Be the first to commenton "At the start of the lengthy unplanned outage for Queanbeyan BESS"
Be the first to comment on "At the start of the lengthy unplanned outage for Queanbeyan BESS"