Embankment rebuild completed at Barron Gorge Hydro Power Station, twelve months after Cyclone Jasper

Tom Metcalfe, the CEO of CleanCo, told ABC Radio Far North Queensland late last month that the rebuild of the earthen embankment at Kuranda Weir was nearing completion. The Kuranda Weir stores water from the Barron River and contains the intake for the 66MW Barron Gorge Hydro Power Station.

During Cyclone Jasper in December 2023, water levels in Kuranda Weir rose above 12 metres – the highest recorded since the power station was built in 1963 – damaging the power station’s water intake and destroying parts of the weir’s embankment.

As a result, both units at the power station were offline for approximately six months while a temporary cofferdam was constructed and the intake was restored.

Further works on a new permanent concrete dam wall are still ongoing, and have been designed to make the weir more resilient to extreme flooding.


About the Author

Dan Lee
Dan is a Market Analyst, who joined Global-Roam in June 2013. After a couple of brief stints overseas, he returned to the team permanently in late 2019. Alongside his work at Global-Roam, he has undertaken short-term contract roles as an analyst and researcher in various areas of the energy sector. Dan graduated from the Master of Sustainable Energy program at the University of Queensland in 2024.

Be the first to comment on "Embankment rebuild completed at Barron Gorge Hydro Power Station, twelve months after Cyclone Jasper"

Leave a comment

Your email address will not be published.


*