As noted in the snapshot from ez2view above, the unit tripped from 308MW in the 15:40 dispatch interval (NEM time), and that this outage was not previously notified in the ‘Generator Outages’ widget in ez2view.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
At 23:05 on Saturday 9th March AEMO advised that the Millmerran power station units 1 and 2 tripped simultaneously at 22:07 (58 minutes prior) – for reasons still unknown.
The publication by AGL Energy of the short note about the transformer incident (and injured worker) at Liddell unit 3 yesterday prompted me to have a quick look, following on from the volatility this week.
A quick look at Saturday 11th April (Easter Saturday) where there were major reductions in output at 4 units across Victoria – 3 coal units in the Latrobe Valley and the Macarthur Wind Farm out in western Victoria, probably related.