As noted in the snapshot from ez2view above, the unit tripped from 308MW in the 15:40 dispatch interval (NEM time), and that this outage was not previously notified in the ‘Generator Outages’ widget in ez2view.
One of three founders of Global-Roam back in 2000, Paul has been CEO of the company since that time.
As an author on WattClarity, Paul's focus has been to help make the electricity market more understandable.
The publication by AGL Energy of the short note about the transformer incident (and injured worker) at Liddell unit 3 yesterday prompted me to have a quick look, following on from the volatility this week.
Be the first to comment on "Unit Trip at Callide B1 on Tuesday 13th February 2024"