On 13th November, NEMMCO released the final version of its report into the Power System Incident “Unplanned Outages of HWTS-LYPS line on 23 July 2008“.
You can find this report on the NEMMCO AEMO website here:
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
The day is not over yet, but we thought you would be interested in the attached snapshot highlighting the first of the occasions on the day when prices jumped to VOLL in SA and VIC as a result of searing temperatures stopping the tennis, and melting VIC and SA into new demand records for each region.
An article at the end of the week in which AGL Energy announced the establishment of a Structured Transition Agreement (STA) with respect to Loy Yang A and the notice of closure for 30th June 2035.
Be the first to comment on "NEMMCO Report: Unplanned Outages of HWTS-LYPS line on 23 July 2008"