Waratah BESS commences full commercial operations
We’re not the only ones who noticed Akaysha Energy’s announcement yesterday (Monday 28th September 2026) that ‘Waratah Super Battery reaches final commercial operations’.
In mid-to-late October 2025, Waratah BESS experienced what’s been described as a ‘Catastrophic Failure’ of one of its three station transformers.
This appears to have been during, or shortly afterwards, Hold Point 5 testing during which the unit was operating at full load.
However it was only on Friday 7th November 2025 that we became aware that something significant had happened:
1) Via changes in MT PASA DUID Availability data
2) Which prompted us to write ‘What’s up with Waratah BESS (unplanned outage till 3rd May 2026)?’.
Since that time, there have been a number of articles written (here, and also elsewhere). Articles relating to this written here are collated together in this category.
We’re not the only ones who noticed Akaysha Energy’s announcement yesterday (Monday 28th September 2026) that ‘Waratah Super Battery reaches final commercial operations’.
After Wednesday's first SIPS test, the Waratah Super Battery successfully completed its second this afternoon, as it inches closer to commercial operations.
A short post to note that the Waratah Super Battery tested its full SIPS capacity of 700MW for around two hours yesterday morning — the first time it was able to do this since last October's transformer failure.
Today (Friday 5th June 2026) a couple of our readers prodded us to notice the News Update ‘Waratah Super Battery now operating at 700MW’ ... so we had a quick look.
Thursday 16th April 2026 is the first time (since we started looking more closely after the long outage began) that Waratah BESS has ramped more than 400MW in a Dispatch Interval.
With the advantage of ‘next day public’ data we can use ez2view to confirm the 2nd (of 3) transformers at Waratah BESS was returned to service Friday evening 10th April 2026.
I’ve been out of the office for ~36 hours and walked back in this afternoon (Friday 10th April 2026) to see that the noted outage profile for the Waratah BESS had changed again.
Another* of our keen readers (and ez2view users) flagged some more machinations to us with respect to Waratah BESS that occurred yesterday (Monday 23rd March 2026).
This article’s a short one triggered by Angela Macdonald-Smith’s article in the AFR on Wednesday afternoon titled ‘Waratah Super Battery faces longer delay in test for NSW grid’.
Probably worthwhile to note that there’s been some recent changes in AEMO market data with respect to the long partial outage for the WTAHB1 unit (late on Tuesday 13th January 2026).
At Wednesday 17th December 2025, it’s approaching 4 weeks since Friday 21st November 2025 (when we last looked at Waratah BESS), so we take an updated look ...
Identifying 5 distinct time periods (from 26th Sept 2025 to 21st Nov 2025) with Waratah BESS, we take ez2view and some external references to try to piece together sequence of events in 3 of these 5 time periods.
On Friday afternoon we asked the question ‘What’s up with Waratah BESS (unplanned outage till 3rd May 2026)?’. It was great to see (on Monday evening) Angela MacDonald-Smith answer some of these questions in the AFR, and then a media update from Akaysha Energy.
Another in the series about Waratah BESS, we have a look at the unit's bids and operations over a 20-day time-range to midnight ending Saturday 8th November 2025.
In the next in the series about Waratah BESS, we have a look at a 9-day time-range to midnight ending Saturday 18th October 2025 via the ‘Bids & Offers’ widget in ez2view.
Relevant to today's questions, we belatedly note now that it was back on Friday 29th August 2025 that the AER published its PASA Compliance Bulletin and Checklist.
Almost exactly 3 months ago we posted a ~12 month chronological record of the history of Waratah BESS. Due to observations today (and questions and conversations leading from them) it was worthwhile to update this trend.
Today we see that, for the WTAHB1 unit in the MT PASA DUID Availability data set, there's now an unplanned outage for Waratah BESS extending well off the page.