AEMO notes possible early-morning direction in NSW on Thursday 25th September 2025
Worth calling out MN129729 published on Wednesday 24th September 2025 at 14:29 about possible early-morning intervention in NSW for System Strength reasons
A catalogue of articles pertaining to eventful days in 2025
Worth calling out MN129729 published on Wednesday 24th September 2025 at 14:29 about possible early-morning intervention in NSW for System Strength reasons
Following from the quick look at the unplanned outage for MP2 (now underway) there's some difference in the picture for the unplanned outage for ER03.
A short note looking at the commencement of the unplanned outage for MP2 on Wednesday morning 24th September 2025
At 15:30 today (Tuesday 23rd September 2025) the AEMO flagged in MN129259 a possible need to intervene in NSW this Thursday 25th September 2025 due to forecast low System Strength.
Coincident with last week's CEC's QCES in Brisbane, the Federal Government announced 16 winners for 'Tender 3' of the Capacity Investment Scheme.
A short article looking at some elevated prices for Regulation Lower FCAS on Sunday afternoon 21st September 2025
We noticed yesterday (Saturday 20th September 2025) a large afternoon dip in frequency down towards (but not outside) the limits of the NOFB - and briefly explore here.
Referencing AEMO's MN129117 published Tuesday 16th September 2025 with respect to this Friday 19th September 2025.
A quick article to explore a frequency drop on Thursday evening 11th September 2025.
Worth a short note to point readers here to the current details about the conference – which is to be held in Brisbane on Tuesday 7th and Wednesday 8th October 2025.
Combining together a bundle of different metrics related to the 'availability' of a wind farm, we take a look at what's happened at Bulgana Wind Farm over the past ~25 months.
A short article to look at the first instance of the new ‘V_NWVIC_GFT1_750’ constraint equation binding - on Wednesday evening 10th September 2025 (not 36 hours after it had first been introduced).
We noticed Bruce Mountain’s comments on LinkedIn about Newport power station running overnight, so had a look in ez2view.
A quick note to call attention to this recent alert from NERC with respect to ‘Large Load Interconnection, Study, Commissioning, and Operations’
A brief look at recent operational challenges at Yallourn unit 4.
Subsequent to earlier article about VP5, the expected duration of the outage pushed out by more than a month.
The AEMO notifies that the new 'V_NWVIC_GFT1_750' constraint equation will first be invoked from 10L00 on Tuesday 9th September 2025.
On Tuesday 26th August 2025 the VP5 unit came offline, with rebid reasons suggesting that ‘turbine vibrations’ were a factor. We take a look ~10 days later.
Today we were alerted that the AEMC had belatedly published this 15-page Staff Working Paper titled ‘Addressing the risk of algorithmic collusion’.
Worth a short note today (Wednesday 3rd September 2025) to record AEMO’s Market Notice 128912 published at 16:10