What was the cause of the coincident trip of Eraring units 1 and 2?
It’s Monday 8th April, the two Eraring units that tripped last week are back online – and I wonder what the cause of the coincident trip was?
Read MoreAt 13:22 (NEM time) on Wednesday 3rd April 2024, there was a coincident trip of two units at Eraring Power Station (ER01 and ER02) whilst ER03 continued to generate.
Here’s a collection of articles pertaining to this…
It’s Monday 8th April, the two Eraring units that tripped last week are back online – and I wonder what the cause of the coincident trip was?
Read MoreAn inspection of bids and dispatch outcomes indicates some units helped compensate for the loss of supply with the trip of ER01 and ER02.
The two Eraring units that had tripped on Wednesday 3 April 2024 were returned to service by 11pm that evening.
Fourth article on Wed 3rd April 2024, pertaining to the earlier coincident trip of ER01 and ER02 units at Eraring Power Station.
AEMO Market Notice 115944 notifies that the coincident trip of ER01 and ER02 was at 13:22 NEM time on Wednesday 3rd April 2024.
In this second short article for the day, we Time-Travel ez2view back to 4 x Dispatch Intervals surrounding the coincident trip of ER01 and ER02 at Eraring Power Station.
A first article noting simultaneous trip of Eraring units 1 and 2 on Wednesday afternoon 3rd April 2024.