Eraring Power Station extension now in MT PASA DUID Availability data
A short follow-on article to this morning’s (about the notice of extension to service for Eraring Power Station) reflecting the update of AEMO data.
A short follow-on article to this morning’s (about the notice of extension to service for Eraring Power Station) reflecting the update of AEMO data.
Thursday morning 23rd May 2024 saw a media News Conference and announcement that Eraring closure will be delayed until August 2027 … or possibly as far out as August 2029.
Following a reminder in a phone call today, I’ve updated the date range in a NEMreview trend previously used in February to look at percentage of Underlying Demand in NSW supplied for each half hour over the 5 day period Monday 6th May 2024 to Friday 10th May 2024 (which includes 3 volatile periods leading to Administered Pricing).
Worth noting these three recent news articles from the past 8 days, all pertaining to the slated closure of the Eraring Power Station as early as 19th August 2025 (under 18 months away), but reporting different perspectives.
A first article today (falling out of analysis for GenInsights Quarterly Update for 2023 Q4) presenting a long-term trend of the incidence of large instances of Aggregate Raw Off-Target across the 44 x operational coal units currently operating in the NEM. A hypothesis as to the cause of recent changes, and some questions …
Following the 4th successive trip/outage at Loy Yang A4 in recent days – and updating Tuesday’s earlier article.
Remembering a question that were were asked by a client in December 2023 (about Yallourn power station) we take a quick look at the start of 2024.
A short article (day after release) about the proposed ‘Orderly Exit Management Framework’ for coal units
A quick note about Eraring Power Station, with the NSW state budget released today (Tue 19th Sept 2023).
Yesterday, the NSW Government released both the Marsden Jacobs report (NSW Electricity Supply and Reliability Check Up) and the Government’s Response.
The 2023 ESOO contains some some reporting (and data) about one particular contingency plan … delaying retirement of existing thermal generators (with Eraring a case in point).
One observation about the 2023 ESOO is that EFOR (equivalent forced outage rate) for coal and large gas units is a large and growing challenge.
Third article today looking back at news with respect to ‘coal closure’ … this article pertaining to EnergyAustralia’s Mt Piper station in NSW.
An article at the end of the week in which AGL Energy announced the establishment of a Structured Transition Agreement (STA) with respect to Loy Yang A and the notice of closure for 30th June 2035.
Friday 14th July 2023 sees some media articles and commentary about several coal-fired generators running longer than previously thought, as the energy transition hits some speed bumps.
Liddell Unit 1 ramped down it’s output to 0MW at roughly 10:30am this morning, signaling the full retirement of Liddell Power Station.
A short article to mark the closure of Liddell unit 2 on Wednesday evening, 26th April 2023.
Latest data from AEMO (from Fri 14th April) suggests Liddell unit 4 might close a couple days later than when we’d looked in February.
AFR and the Australian (and elsewhere?) there are reports of the co-owner of Callide C (with CS Energy) being placed in voluntary administration.
Given the significance of the event (Reserve Trader almost triggered on Thursday 16th March – 34 days till the closure of Liddell Unit 4) we’re investing some time in exploring more detail of the event. This is Part 1.