Palmerston to Waddamana lines returned to service on December 2, 2022
A successful return to service for the Waddamana to Palmerston 220 kV lines following damage sustained during landslides on 14 October 2022.
A successful return to service for the Waddamana to Palmerston 220 kV lines following damage sustained during landslides on 14 October 2022.
Third article on what happened on Friday 14th October 2022 – sharing a photograph of the damaged transmission (thanks to TasNetworks for the photo, and Zeus for the weather) and outlining a number of different timescales that could be considered with respect to this event.