Callide B2 commences return to service, Friday morning 13th June 2025
Approximately 8 hours after the return to service journey at Loy Yang A1 commenced, a similar journey has been commenced at Callide B2 this morning.
Approximately 8 hours after the return to service journey at Loy Yang A1 commenced, a similar journey has been commenced at Callide B2 this morning.
The volatility of Thursday evening 12th June 2025 had ended by that time (though not by much), but it’s worth noting that the Loy Yang A1 unit commenced its return to service journey last...
A short article to note that Callide C3 came back online in the early hours of Sunday morning 1st June 2025.
No sooner had I published this article about ‘Berrybank 1 Wind Farm recommences operations, on Friday morning 7th February 2025’ than I received an ez2view alert on the restart of neighbouring Berrybank 2 Wind...
Third article in a series, following the turbine failure at one of the Berrybank Wind Farms (was it Berrybank 2?) ... to note that Berrybank 1 has restarted on Friday 7th February 2025.
This morning at 07:25 the ‘Notifications’ widget in ez2view alerted us that ER03 had reached a ‘first output’ milestone during the return-to-service journey.
Given forecasts for early next week in NSW, it’s some welcome news to see that the BW04 unit has commenced its return to service process.
Two weeks after our last look at the Return To Service progress at Callide C4, here's a quick update as at Friday 20th September 2024.
A short update (on Friday 6th September 2024) about Callide C4, which has come off for a planned outage as part of its (re)commissioning process.
It's Friday 30th August 2024 and Callide C4 has commenced its return-to-service (and re-commissioning), after an outage lasting 1193 days
After a forced outage lasting almost 4 weeks, Callide C3 came back online Wednesday evening 21st August 2024.
CleanCo have announced the RTS of Barron Gorge Unit 1 and 2 after a ~6 month outage following significant damage from Cyclone Jasper.
Worth noting that on Friday evening 21st June 2024 Kogan Creek came back online, ~36 hours after it had come offline.
A glance at our generator outages widget shows a further three week delay to the expected RTS of Callide Unit C4.
On Friday 21st June 2024 the unit 2 of Barron Gorge hydro facility has started up - the next step in a repair process following TC Jasper six months ago.
Eraring Unit 2 commenced return to service on Saturday afternoon 25th May 2024.
A quick update on the return to service expectation on Barron Gorge hydro power station.
At the end of an eventful week in the NEM, here's an update on a few fronts with respect to Callide C.
On Tuesday morning 21st May 2024 the Vales Point 6 unit has returned to service, ~2 days earlier than earlier expectations.
On Thursday afternoon 16th May 2024, Eraring unit 2 (after a 15-day outage due to a boiler tube leak) has commenced the return-to-service process.