Two curiosities about upcoming outages at Eraring Power Station

A short article for Monday 5th October 2026, with this snapshot from two widgets in ez2view highlighting two points that spiked my interest in Origin’s Eraring Power Station, in the coming weeks:

2026-10-05-at-10-20-ez2view-EraringUnits

 

Per the numbering:

1)  This coming Saturday (10th October 2026) sees a period where the 3 x Eraring units that are slated to run will all be at lower Availability from half-hour ending 02:30 to half-hour ending 21:30 on the day:

(a)  It’s been in the MT PASA DUID Availability data for some time, but is now also shown in the ST PASA outlook horizon (now that we’re within that window, and the MT PASA DUID Availability data updates have ceased, and become ‘stale’ in the ‘Unit Outages’ widget

(b)  Am curious if to do with some common component onsite, or outside in the network – but have not invested time to check?

2)  We also see that:

(a)  today ER03 is off for a lengthy ‘unplanned maintenance outage’ (and ER01 is not running)

(b)  but the point of interest is that:

i.  a few days after slated return of ER03 (Wednesday 22nd October 2026) …

ii.  it’s sibling ER04 has been slated to come off for a similar lengthy ‘unplanned maintenance outage’ (from Saturday 25th October 2026)

iii.  and then (off the scroll to the right) the same plan seems to be in place for ER02 when its other sibling ER04 returns to service (‘unplanned* maintenance outage’ from 22nd November 2026)

iv.  apart from the curious irony (* of an ‘unplanned’ maintenance outage being scheduled well over a month in advance), I wonder if something’s been found that’s common to all 4 units?


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

Be the first to comment on "Two curiosities about upcoming outages at Eraring Power Station"

Leave a comment

Your email address will not be published.


*