Today (Thursday 2nd April 2026) we noted the following ‘Notification’ widget alert in ez2view triggered at 11:36 (NEM time) flagging a relatively large drop in output for a relatively small unit:
Here’s a snapshot of the ‘Unit Dashboard’ widget we grabbed in real time at 12:45 (NEM time), noting some what might be some hiccups:
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
No sooner had I published this article about ‘Berrybank 1 Wind Farm recommences operations, on Friday morning 7th February 2025’ than I received an ez2view alert on the restart of neighbouring Berrybank 2 Wind Farm.
On Friday 5th December 2025 we also saw EnergyAustralia report to AEMO the 19-day extension to the lengthy unplanned outage at YWPS2 following ‘LP turbine issues’ experienced in August 2025.