Recapping operations at Waratah BESS (including enablement for SIPS) … to August 2025

As noted on Tuesday this week, I’ve just returned from over a month away (and disconnected from the NEM), and have been striving to catch up.

As noted in that article, one of the things I noticed was that Waratah BESS recently was ‘switched on’ in relation to the System Integrity Protection System (SIPS) services it’s been contracted to provide:

  • Which will enable some support for the grid, to enable more VRE generation
  • But (again, coming back up to speed) I think*
    • only under ‘System Normal’ conditions (i.e. no network outages)
    • and only for Thermal constraints (i.e. there might be some limitations on its usefulness in cases such as transient stability risks etc)

 * if I am incorrect here, can some readers please point this out in comments below?

 

So (trying to kill a few birds with one stone – including getting me back up to speed) I thought it would be useful to piece together this article for some Friday afternoon reading…

 

A trend over time

Powering back up with the ez2view ‘Trends Engine**’ I have prepared the following high level overview of some daily stats with respect to the WTAHB1 unit in the AEMO MMS database.

** noting new release on this imminent, including enhancements based on customer requests and feedback etc.

2025-08-08-ez2view-Trends-WTAHB1-DailyStats

Remember that

  • (post IESS) the charging side of any battery (now a BDU) is shown as negative numbers.
  • to click on the image for a full screen view

 

Key events in its lifetime (to date)

In reverse chronological order, I’ve tabulated a few key dates and events in its limited life to date (there are other things that I might come back and add in later):

 

Date, or Date Range Description of Event

August 2025

Worth readers noting two (other) things with respect to the month of August (in addition to the below):

Additional Observation #1)  We see in the chart above that:

    • the peak ENERGY discharge from the battery, to date, has been at the rate of 369MW:
      • on 17th June 2025 … and then on some days subsequently
      • but note that this does not include any enablement for Raise FCAS services.
    • but note that this is under half of the registered Maximum Capacity of the unit (850MW)

Additional Observation #2)  It’s worth noting (with respect to the note below about May 2024) that 19th August 2025 was the date at which Eraring Power Station had earlier been slated to close.

 

Fri 1st August 2025

A week ago (on Friday 1st August at 18:30) the AEMO communicated by MN128419 that:

‘——————————————————————-
MARKET NOTICE
——————————————————————-

 From :              AEMO
To   :              NEMITWEB1
Creation Date :     01/08/2025     18:30:34

 ——————————————————————-

 Notice ID               :         128419
Notice Type ID          :         GENERAL NOTICE
Notice Type Description :         Subjects not covered in specific notices
Issue Date              :         01/08/2025
External Reference      :         New South Wales – Waratah Super Battery System Integrity Protection Scheme (SIPS) In-Service

 ——————————————————————-

 Reason :

 AEMO ELECTRICITY MARKET NOTICE.

 The Waratah Super Battery System Integrity Protection Scheme (SIPS) has been enabled by TransGrid at 1758 hrs 01/08/2025.

 Manager NEM Real Time Operations

 ——————————————————————-
END OF REPORT
——————————————————————-’

So that’s big (and welcome) news!

This was flagged in various official locations, including:

1)   On 5th August Akaysha Energy wrote ‘The Waratah Super Battery is online’; and

2)   On 5th August EnergyCo wrote ‘Waratah Super Battery Project begins partial operation as shock absorber for NSW grid’.

3)   On 5th August TransGrid wrote ‘Transgrid specialists deliver Australian-first control system to support Waratah Super Battery Project’.

It was also picked up in the media, including the following:

1)  On 4th August on RenewEconomy, Giles Parkinson wrote ‘Australia’s most powerful battery is now officially operating as the grid’s biggest shock absorber’.

2)   On 5th August via the ABC, Sarah Forster wrote ‘Waratah Super Battery connected to NSW power grid and switched on’.

3)  Of course, I noted it here at the start of this week.

… and elsewhere

June 2025

It had been rumoured ahead of time in various media articles, but worth noting the Powin (the manufacturer/supplier of the battery in the US) filed for Chapter 11 bankruptcy protection in June 2025.

This was flagged in various locations, including:

1)   On 11th June in Energy Storage, Andy Colthorpe wrote ‘Powin files for Chapter 11 bankruptcy protection and spins off project services business’;

… and elsewhere …

earlier 2025

Earlier in 2025, there had been comments I’d seen about the longer-than-(some-had)-expected construction and commissioning time for the Waratah BESS.

When time permits, I might return here and add in some direct links to those articles – but it did remind me of Dan Lee’s earlier article ‘Need for speed: How long has each battery project in the NEM taken to deliver?’ which:

  • was from 15th March 2024 (so prior to Waratah even registering on the list).
  • but still speaks to the ‘sometimes these take much longer than initially thought’ consideration.

27th Nov 2024

Thinking back now, the end of November and early December 2024 was both:

  • A period of tight supply-demand balance (and hence volatility) in the NEM:
  • But it was also another period where I’d been away on holiday.

The (still very much in commissioning) Waratah BESS saw some action during this period, and received some attention as a result.

For instance, Dan Lee had written at the time that ‘Waratah BESS also directed to maintain state of charge on Wednesday afternoon, 27th Nov 2024’.

Elsewhere, others had been a bit more exuberant about the performance of this and other batteries (even in terms of them ‘saving the day’) so it’s useful to reflect on the article by Dan Lee the next day noting ‘NSW seemingly squeaked through yesterday: Was it even that hot? Did batteries save the day?’.

Sept 2024

It was early September 2024 when the battery was registered within the AEMO’s MMS systems, as we can see from the

It was later in September 2024 when we saw the first small slices of discharge.

We saw progress for the month noted:

1)  On 9th September in Power Technology, Claire Jenns wrote ‘Waratah Super Battery completes energisation first stage, boosts Australia’s BESS sector’.

… and elsewhere

May 2024

Many readers will recall that it was on Thursday 23rd May 2024 that the announcement was made that ‘Eraring Power Station closure delayed by 2 years (or maybe 4?)’.

I’ve included this here because amongst the (many other!) reasons for the extension being required were considerations about the timing of full commercial operations of the Waratah BESS.

14th Dec 2022

As noted here on the AER website:

‘On 17 October 2022, Transgrid submitted a revenue proposal to the AER for the System Integrity Protection Scheme SIPS (battery) Service component of the WSB project, seeking to recover the cost of payments it will make to the battery service provider. In December 2022 we made a determination setting out the amounts that Transgrid is to be paid.  .’

14th Oct 2022

As noted here on the AER website:

‘On 14 October 2022, the NSW Minister for Energy directed Transgrid as the Network Operator to carry out the Waratah Super Battery (WSB) project, which is classified as a Priority Transmission Infrastructure Project under the EII framework.’

I’ve included this quote here:

  • To help readers understand the broader timeline in this development;
  • But also because the NSW Government page the AER linked to is now no longer at that address (and I’ve not invested time to find the source)

 

If readers see I have missed (or misunderstood) significant event(s), please feel free to add comments … and note that I might return later, to add in more details (as a useful future source of linkages about the Waratah BESS).


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

1 Comment on "Recapping operations at Waratah BESS (including enablement for SIPS) … to August 2025"

  1. Just on Waratah’s maximum discharge to date Paul, where you mention that it doesn’t include any Raise FCAS enablement volume – the battery isn’t yet registered to deliver FCAS, I guess that will come later in its commissioning programme.

Leave a comment

Your email address will not be published.


*