Next stage of testing for PEC Stage 1 scheduled to begin tomorrow afternoon (Thursday 31st October 2024)

Apologies to readers that this short article might be a bit cryptic – a client called up this afternoon asking about the next milestones in the testing of PEC Stage 1 …. remembering that:

1)  PEC Stage 1 is ‘simply’ being modelled within NEMDE as an upgrade to the Heywood interconnector;

2)  and that it’s not until PEC Stage 2 (many months away yet) before we see the introduction of a new NSW1-SA1 interconnector in the AEMO’s EMMS and NEMDE logic.

 

So I took a quick look at the ‘Constraint Sets’ widget within ez2view and filtered quickly to look for ‘PEC’ and/or ‘Heywood’ in the constraint description and see this:

2024-10-30-at-15-45-ez2view-ConstraintSets

Readers following on with their own copies of ez2view can then drill further into the ‘Constraint Set Details’ widget and the ‘Constraint Dashboard’ widget to understand more…

 

Other articles about Project Energy Connect:

1)  Might have been added to this specific category here on WattClarity®;

2)  But there a broader number of articles tagged with ‘Project Energy Connect’.


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.

1 Comment on "Next stage of testing for PEC Stage 1 scheduled to begin tomorrow afternoon (Thursday 31st October 2024)"

  1. Whoops, delayed again 🙄