I’d just finished a conversation with a WattClarity reader this morning noting that AEMO had not issued any notice to say RERT had actually been contracted yesterday (following negotiations noted firstly here and then here (in the context of prices at the time)), so there may have been no cost incurred …
… and (lo and behold!) the following Market Notice arrives:
——————————————————————-
MARKET NOTICE
——————————————————————-
From : AEMO
To : NEMITWEB1
Creation Date : 15/12/2023 07:42:53
——————————————————————-
Notice ID : 112370
Notice Type ID : MARKET INTERVENTION
Notice Type Description : Reserve Contract / Direction / Instruction
Issue Date : 15/12/2023
External Reference : ENTERED INTO RERT CONTRACTS
——————————————————————-
Reason :
AEMO ELECTRICITY MARKET NOTICE.
AEMO Intervention Event, Reliability and Emergency Reserve Trader (RERT) – NSW1 Region – 14/12/2023
Refer to AEMO Electricity Market Notice no. 112333.
AEMO has entered into a reserve contract to maintain the power system in a Reliable operating state during the following period of time;
15:30 to 19:30 hrs 14/12/2023
The latest time to activate or dispatch these reserves has now passed. No reserve contracts were activated or pre-activated.
Manager NEM Real Time Operations
——————————————————————-
END OF REPORT
——————————————————————-
Not sure why only published this Market Notice this morning?
Be the first to comment on "Belated notice from the AEMO about RERT contracted for yesterday (Thu 14th Dec 2023)"