As can be seen here in this snapshot from ez2view at 22:45, unit 1 has already returned to service – and we presume that this might be followed by unit 2 (unless it is damaged in some way).
The bid data (available from 04:00 tomorrow) might reveal more but, for now, all we have is conjecture and rumour…
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
Following some questions yesterday (from clients and others) we take a quick look at how Yallourn Power Station is progressing in coming back from outage caused by inundation from the nearby river.
I’ve already noted about the appropriateness of holding the EUAA National Conference this week … with gas and electricity spot prices being elevated as they have been in recent times! This evening (Monday 9th May 2022) market volatility has put…
Be the first to comment on "2 x Loy Yang A units offline this afternoon"