In the prior article we noted the tripping of four separate units (three at Yallourn – possibly due to some network issues). So we’ve guessed which-sat-where in the time-series frequency trace.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
Some wobbles in System Frequency (NEM mainland) through the middle of the day on Thursday 31st October 2024 stick out, and will be progressively explored.
This is the 2nd of 4 Case Studies to follow on from Tuesday’s main article (summarising results across 105,120 dispatch intervals through 2019 for ‘all Coal’ and ‘all Wind’ groupings). In this case, let’s look at the ‘worst’ case, in aggregate, where coal units over-performed compared to dispatch targets.
Some operations at Stanwell Power Station unit 1 in the past couple weeks caught our attention, and are presented as a useful illustration of some concepts related to flexibility of power generators (in this case, coal-fired power).