Outage at Vales Point unit 5 extended – return to service now not expected until 15th December 2025
Subsequent to earlier article about VP5, the expected duration of the outage pushed out by more than a month.
Subsequent to earlier article about VP5, the expected duration of the outage pushed out by more than a month.
On Tuesday 26th August 2025 the VP5 unit came offline, with rebid reasons suggesting that ‘turbine vibrations’ were a factor. We take a look ~10 days later.