Unplanned outage of Dapto – Marulan (8) 330 kV line
At 07:55 (on Monday 20th October 2025), an unplanned outage of Dapto - Marulan (8) 330 kV line led to the unplanned invocation of the 'N-DTMN_8_15M' constraint set.
At 07:55 (on Monday 20th October 2025), an unplanned outage of Dapto - Marulan (8) 330 kV line led to the unplanned invocation of the 'N-DTMN_8_15M' constraint set.
A quick note, on Monday morning 20th October 2025, showing the re-emergence of price forecasts up near the Market Price Cap for a 90-120 minute period this afternoon/evening.
Following a series of Market Notices from AEMO with respect to forecast LORx conditions for NSW next Wednesday 22nd October 2025, we take a first look.