Wobbles at Yallourn unit 4
A brief look at recent operational challenges at Yallourn unit 4.
A collation of articles pertaining to Friday 29th August 2025.
A brief look at recent operational challenges at Yallourn unit 4.
In this article we take a look at operations of Waratah BESS through August 2025 - including some large Dispatch Errors on several days: (a) including Fri 29th Aug 2025, and how WTAH1 apparently...
Taking a second look at the midday decay of mainland frequency on Friday 29th August 2025.
As a further update on outage expectation for the damaged YWPS2 (which tripped with 'LP turbine issue' on Tue 26th August) the latest return to service expectation is now not until 22nd October 2025.
As another case of frequency disruption on the mainland grid, we spotted this trend occurring just before midday on Friday 29th August 2025.
Part 3 in an evolving series of articles about a series of the network outage(s) on the Tailem Bend - Tungkillo 275kV line that's driven LOWER1SEC prices through the roof and triggered Administered Pricing...