The extended outage at Eraring unit 3 (as at Thu morning 5th Dec 2024)
We thought we’d take a quick look at Eraring unit 3, given it was the focus of Colin Packham’s article yesterday in the Australian.
We thought we’d take a quick look at Eraring unit 3, given it was the focus of Colin Packham’s article yesterday in the Australian.
Partly prompted by a comment yesterday from a WattClarity reader (Liam), and powered by ‘next day public’ data, we take a look at Yallourn Power Station on Tuesday 12th November 2024.
A second quick look at the drop in NEM Mainland Frequency on Tuesday 12th November 2024.
On Sunday 8th September 2024 the Herald Sun published an article speculating about possible Service Life extension to Yallourn Power Station.
A quick look at several different coal-fired units, via the ‘Generator Outages’ widget in ez2view.
A short article noting ER01 and YWPS3 offline for Unplanned Maintenance/Forced Outages, and another coming soon for ER02
Yallourn unit 1 has just come offline for its Major Planned ‘performance improvement’ outage – but coincident with that, Yallourn unit 3 is suffering from a run of forced outages.
A short article to mark the start of the long planned outage for Yallourn unit 1, which is aimed (at least in part) at improving the performance of the unit following 2022.
A client question (for GenInsights Quarterly Updates) recently prompted a quick look at the delay to the start of the planned outage for Yallourn Unit 1.
Five days after Tuesday 13th February 2024 we have a bit of time to take this initial (top-down) look at bidding for ENERGY in the Victorian region on that day … with 27 Questions/Observations identified!
Remembering a question that were were asked by a client in December 2023 (about Yallourn power station) we take a quick look at the start of 2024.
With ez2view v9.8.5.1 released yesterday (Tue 30th Sept 2023) with enhancements to ‘Generator Outages’ we take the opportunity of some questions about Kogan Creek Power Station to have a look at the usefulness, and possible additional tweaks to make, to this software widget.
Yesterday (Wed 18th Oct 2023) Origin Energy held its Annual General Meeting, with discussion wide-ranging. Here’s two things that jumped out to me about the Eraring Power Station, which is currently slated to close in 2025.
A belated and back-dated article to point to the EnergyAustralia Media Release of 7th August 2023 about the $400 million outage plans for Yallourn for 2023 and 2024.
It does not happen often, so when receiving 4 different ‘coal unit off’ alerts within 24 hours, we thought we would take a look …
Prompted by the massive loss reported by CLP for its EnergyAustralia business, and plans for major outages for 4 units at Yallourn, we took a quick look using ez2view at outage plans.
A belated and back-dated article to point to the EnergyAustralia Media Release of 8th August 2022 following the Energy Crisis.
A short article about the fire in the Yallourn power station coal bunker.
A short record of gas prices being up at $20/GJ and above through a cold spell for winter, with other factors at work.
On Friday evening (2nd July 2021) Yallourn 4 returned to service