Hunter GT (a.k.a. Kurri Kurri) now not expected till 1st September 2026
The expected operations date for both units at Hunter GT has been pushed back until 1st September 2026.
The expected operations date for both units at Hunter GT has been pushed back until 1st September 2026.
Looking at the MT PASA DUID Availability data for Kidston Pumped Hydro, which shows the expected first availability (July 2027) is ~10 months later than earlier expectations.
One of our keen readers (and ez2view users) has flagged this to us – so we thought we’d post this short note using ez2view to look at delays at the Kurri Kurri peaker (HUNTER GT).
Recent debate has centred on the CIS’s success so far. In part one of this four-part series, we look at how projects have progressed since being awarded a contract.
Alice Matthews examines how approval times for renewables vary widely by state and technology — with NSW wind projects facing the longest delays.
Part 2 of this analysis into the latest update of the ESOO, its modelling, and the project development pipeline.
Following Colin Packham's article in the Australian, we take a look in the market data at EnergyAustralia's Tallawarra B
A compiled list of development projects delayed or leaving the market in between the ESOO2023 and its update released two weeks ago. Along with some analysis of longer term trends with the development pipeline.