Aldoga Solar Farm on Sunday 12th October 2025 – Part 2
In this article we inspect power deviations from dispatched units that would have contributed to the frequency rise, and the deviations that would have contributed to the correction.
In this article we inspect power deviations from dispatched units that would have contributed to the frequency rise, and the deviations that would have contributed to the correction.
A quick initial look at two lengthy periods of Non-Conformance at Aldoga Solar Farm on Sunday 12th October, with the first period seeing large negative Dispatch Error, and a blip in system frequency.