Eraring Unit 2 commences return-to-service startup, but ….

In this morning’s first article (which was about Callide C), I’d noted the expectation of return-to-service sometime today for Eraring Unit 2 whilst utilising the ‘Generator Outages’ widget in ez2view .

Well, one of the other widgets in ez2view this afternoon (the ‘Notifications’ widget) has triggered us this alert on seeing the ER02 unit switch back on in the FinalMW for 15:20:

2024-05-16-at-15-25-ER02-startsup

Here’s a snapshot of the ‘Bids & Offers’ widget in ez2view filtered to look back 20 days, so highlighting both:

1)  The outage beginning late on Wednesday 1st May 2024 (due to a boiler tube leak); and

2)  The start of a return-to-service profile ~15 days later, on Thursday 15th May 2024:

2024-05-16-at-15-45-ez2view-BidsOffers-ER02

Let’s hope it goes smoothly.

 

PS1 at Friday 17th May 2024 at 07:45

The return to service hit a snag overnight, as noted in Friday’s first article ‘… but ER02 return to service hit a snag (Thu 16th May 2024) – now possibly out until Tue 21st May 2024’.


About the Author

Paul McArdle
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients. Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.