Given that the fire onsite at (on Wednesday 2nd September 2026) ‘destroyed Tungatinah Power Station’ (to quote Hydro Tasmania) it will surprise noone that today (Monday 5th October 2026) Hydro Tasmania has updated the MT PASA DUID Availability data for the station to show a more staggered (and much longer) return-to-service path.
Of course, it’s quite likely (almost certain, I’d expect) that there will be further evolution of this plan – given it was only a month ago the fire occurred onsite.
Paul was one of the founders of Global-Roam in February 2000. He is currently the CEO of the company and the principal author of WattClarity. Writing for WattClarity has become a natural extension of his work in understanding the electricity market, enabling him to lead the team in developing better software for clients.
Before co-founding the company, Paul worked as a Mechanical Engineer for the Queensland Electricity Commission in the early 1990s. He also gained international experience in Japan, the United States, Canada, the UK, and Argentina as part of his ES Cornwall Memorial Scholarship.
In the last MT PASA DUID Availability data update for Friday 12th July 2024 the return to service expectation for the repaired Callide C4 unit has been delayed again another 40 days … now 50 days out, till Saturday 31st August 2024.
1 Commenton "A more staggered (and much longer) return-to-service path for the destroyed Tungatinah Power Station"
Given the structural steelwork in the building is also severely damaged and they won’t even have a functional overhead crane to start pulling things apart it is almost like a new build. Good luck with even these dates. Given the age of the kit, you will almost be redesigning around new (commercially available) equipment rather than trying to reproduce what was there. It’s just little things like the old steelwork will be imperial dimensions and new will be metric. Nothing fits properly. Will be a long, often frustrating but very interesting challenge for the engineers involved.
Given the structural steelwork in the building is also severely damaged and they won’t even have a functional overhead crane to start pulling things apart it is almost like a new build. Good luck with even these dates. Given the age of the kit, you will almost be redesigning around new (commercially available) equipment rather than trying to reproduce what was there. It’s just little things like the old steelwork will be imperial dimensions and new will be metric. Nothing fits properly. Will be a long, often frustrating but very interesting challenge for the engineers involved.