Frequency drop on Thursday evening 11th Sept 2025 with Tallawarra B trip
A quick article to explore a frequency drop on Thursday evening 11th September 2025.
A quick article to explore a frequency drop on Thursday evening 11th September 2025.
A zoomed-out view of six metrics supports understanding of physical/technical semi-scheduled generator availability.
Worth a short note to point readers here to the current details about the conference – which is to be held in Brisbane on Tuesday 7th and Wednesday...
Combining together a bundle of different metrics related to the 'availability' of a wind farm, we take a look at what's happened at Bulgana Wind Farm over the...
A short article to look at the first instance of the new ‘V_NWVIC_GFT1_750’ constraint equation binding - on Wednesday evening 10th September 2025 (not 36 hours after it...
We noticed Bruce Mountain’s comments on LinkedIn about Newport power station running overnight, so had a look in ez2view.
A quick note to call attention to this recent alert from NERC with respect to ‘Large Load Interconnection, Study, Commissioning, and Operations’
A brief look at recent operational challenges at Yallourn unit 4.
In this article, we tie together various events since 1st January 2024 that featured either System Frequency outside the NOFB and large AggROT for Semi-Scheduled assets.
Subsequent to earlier article about VP5, the expected duration of the outage pushed out by more than a month.
The AEMO notifies that the new 'V_NWVIC_GFT1_750' constraint equation will first be invoked from 10L00 on Tuesday 9th September 2025.
On Tuesday 26th August 2025 the VP5 unit came offline, with rebid reasons suggesting that ‘turbine vibrations’ were a factor. We take a look ~10 days later.
We count the number of days each month when there was at least one 4-second measurement outside the NOFB.
Today we were alerted that the AEMC had belatedly published this 15-page Staff Working Paper titled ‘Addressing the risk of algorithmic collusion’.
Worth a short note today (Wednesday 3rd September 2025) to record AEMO’s Market Notice 128912 published at 16:10
How common is it that mainland frequency deviates outside the NOFB (normal operating frequency band)?
It was no surprise at all to open the AFR and see 4 different analysts quoted in voicing their concerns about the unrealistic notion that Eraring can close...
Looking back to Wednesday 27th August 2025, when Tamar Valley CCGT switched off.
In this article we take a look at operations of Waratah BESS through August 2025 - including some large Dispatch Errors on several days: (a) including Fri 29th...
Taking a second look at the midday decay of mainland frequency on Friday 29th August 2025.